  本文选题:分区开采 + 露天煤矿 ; 参考:《辽宁工程技术大学》2015年博士论文


【摘要】:我国大型露天煤矿多采用分区开采,相邻采区间必然存在一个转向过渡接续的技术难题。通过对转向方案及转向期间的采剥工程问题进行研究,深入剖析不同转向方案的工程特点、适用范围,明确了主要影响因素,通过理论分析、实验室试验、数值模拟,建立了剥采工程优化模型,并应用于安家岭露天煤矿转向过渡工程中,验证了优化模型的正确性。基于不同转向方式的工程特点、适用范围,明确了采区接续期间的限制因素和优化目标,并进行了建模量化分析,基于分区开采露天煤矿基本转向方式,提出了剥采工程量表叠加法确定采区接续工程位置确定方法。根据转向期间的边坡服务性质、周期和稳定性要求等基本参数,分类讨论了边坡的几何及力学特征,提出了采区接续期间,边坡的安全管理和时效优化分析方法。对不同转向方式的特点和约束条件进行分析,明确了连续型和间断型转向方式的主要约束条件,建立了考虑设备、资金约束及时效边坡与经济运距的露天煤矿不同转向方式的综合评价模型。针对安家岭露天煤矿开采条件和剥采排工程现状,对露天矿的首采区向二采区转向接续方案进行研究,提出了四种转向接续方式,综合边坡和经济耦合的目标,利用综合优化模型确定了安家岭露天煤矿最佳转向方式为“L”形转向方案,确定了合理接续工程位置。
[Abstract]:The large open pit coal mines in China are mostly zonal mining, and there must be a technical problem of transition in adjacent mining areas. Through the study of the steering scheme and the mining and stripping engineering during the steering period, the engineering characteristics and applicable scope of the different steering schemes are analyzed in depth, and the main influencing factors are defined. Through theoretical analysis, laboratory tests, numerical simulation, The optimization model of stripping project is established and applied to the transition project of Anjialing opencast coal mine, and the correctness of the optimization model is verified. Based on the engineering characteristics of different steering modes and the scope of application, the limiting factors and optimization objectives during the continuation of mining areas are defined, and the modeling and quantitative analysis are carried out. In this paper, a method of determining the position of the continuous project in the mining area by the method of superposition of stripping and mining works is put forward. According to the basic parameters of slope service, period and stability, the geometric and mechanical characteristics of slope are classified and discussed, and the methods of slope safety management and time-dependent optimization analysis are put forward. The characteristics and constraint conditions of different steering modes are analyzed, the main constraint conditions of continuous and discontinuous steering modes are defined, and the equipment is established. Comprehensive evaluation model of different steering modes of open-pit coal mine with fund constraint and time-limited slope and economic transportation distance. In view of the mining conditions and the current situation of stripping and drainage engineering in Anjialing opencast coal mine, the paper studies the scheme of turning from the first mining area to the second mining area of the open-pit mine, and puts forward four kinds of steering connection modes, which synthesizes the target of slope and economic coupling. The optimal steering mode of Anjialing opencast coal mine is "L" shape steering scheme, and the reasonable position of continuous project is determined by using the comprehensive optimization model.
【学位授予单位】:辽宁工程技术大学
【学位级别】:博士
【学位授予年份】:2015
【分类号】:TD824

【相似文献】

相关期刊论文 前10条

1 刘宪权,李志强,史建华;分区开采转向接续期间存在的问题及对策[J];露天采煤技术;2001年04期

2 李建军,范效斌;龙门山石灰石矿分区开采方案分析[J];中国矿业;2004年04期

3 孙毅民;杨智超;;纵向分区开采的设计实践[J];现代矿业;2011年09期

4 谢永生;;陡帮分区开采工艺在穆利亚希露天铜矿的应用[J];有色金属(矿山部分);2012年02期

5 刘维玉;分区开采转向期间的生产接续技术[J];露天采煤技术;1996年04期

6 丁新启;安太堡露天煤矿的分区开采及转向接续[J];露天采矿技术;2003年02期

7 戴九山;露天矿分区开采及其年度剥离量的确定[J];煤矿设计;1980年05期

8 李克民;张幼蒂;;露天矿分区开采优化数学模型[J];金属矿山;1992年03期

9 黄光球;露天矿多分区开采采剥关系动态优化方法[J];冶金矿山设计与建设;1995年06期

10 王斌,尚涛;分区开采转向后开拓运输系统的优化[J];露天采矿技术;2004年01期

相关会议论文 前1条

1 范天文;刘辉;潘洪伟;;马城铁矿分区开采方案的探讨[A];第二十届“冀鲁川辽晋琼粤”七省矿业学术交流会论文集[C];2013年

相关重要报纸文章 前1条

1 本报记者 张丽君 通讯员 乔廷宇;敢破常规天地宽[N];中国冶金报;2000年

相关博士学位论文 前1条

1 王肇东;分区开采露天煤矿采区接续剥采工程优化研究[D];辽宁工程技术大学;2015年

相关硕士学位论文 前1条

1 丁新启;单斗卡车工艺分区开采程序研究及应用[D];辽宁工程技术大学;2002年