[Abstract]:In order to improve the recovery rate of coal resources in Yanjiahe coal mine, prolong the service life of the coal mine and realize rational mining between the thick and thin coal seams in the coal seam group, this paper bases on the geological conditions of 5-1 coal, 5-2 coal and 8 coal in the coal seam group. Using the methods of theoretical analysis, physical simulation, numerical simulation, field measurement analysis and so on, the up-going mining technology of fully mechanized caving mining under the close distance coal seam group is deeply studied. Based on the comprehensive analysis of the overlying rock migration and breaking characteristics of 8 coal fully mechanized caving mining stope, the deformation and failure characteristics of overlying 5-1 coal and 5-2 coal strata, the feasibility of upward mining and the 5-1 coal are determined. 5-2 coal face reasonable arrangement and other key parameters. The main results are as follows: (1) theoretical analysis shows that the 5-1 coal seam is located in the upper layer of the caving zone above the goaf of No. 8 coal face and the lower layer of the fracture zone; The 5-2 coal seam is located in the transitional zone between the caving zone and the fracture zone above the goaf of No. 8 coal face. (2) the analysis of overlying rock migration and fracture characteristics of stope shows that the height of overlying rock collapse zone is about 25m and the height of fracture zone is 350.60m; Coal seam 5-1 is above the 8th coal caving zone, and the roof and floor of coal seam 5-1 are in good continuity, and there is no step sinking. The damage of 5-2 coal is more serious than that of 5-1 coal. (3) the height of 8 coal caving zone measured by borehole observation is about 25m.5-2 coal roadway, the roof and floor does not appear step subsidence, the coal seam appears whole subsidence, and the continuity is intact. It can be mined up. When one side of 8 coal goaf is solid coal seam or 8 coal section coal pillar is wide pillar (20m), 5-2 coal face should be arranged in the same slot and 8 coal goaf should not be less than 25m. (4) the comprehensive analysis above shows that after 8 coal fully mechanized caving mining, 8 coal fully mechanized caving mining, The overlying coal seam 5-1D 5-2 is in the whole subsidence, and the coal seam structure continuity is intact; Except for cutting, stoppage and the upper part of the upper end of the working face, there is no step dislocation in the 5-1D 5-2 coal seam, so it can be mined up.
【学位授予单位】:西安科技大学
【学位级别】:硕士
【学位授予年份】:2017
【分类号】:TD823.81
【参考文献】
相关期刊论文 前10条
1 邵小平;武军涛;张嘉凡;张杰;;上行开采覆岩裂隙演化规律与层间岩层稳定性研究[J];煤炭科学技术;2016年09期
2 黄鹏;李百宜;肖猛;陈志维;裴玉龙;;近距离煤层充填上行开采临界充实率设计[J];采矿与安全工程学报;2016年04期
3 姜耀东;杨英明;马振乾;李彦伟;;大面积巷式采空区覆岩破坏机理及上行开采可行性分析[J];煤炭学报;2016年04期
4 王红胜;由临东;李树刚;双海清;杜政贤;;复杂地质条件煤层群开采矿井合理生产能力分析[J];西安科技大学学报;2015年03期
5 王红胜;李树刚;张新志;吴林梓;董永建;双海清;;沿空巷道基本顶断裂结构影响窄煤柱稳定性分析[J];煤炭科学技术;2014年02期
6 王红胜;张东升;李树刚;王琳;吴林梓;;基于基本顶关键岩块B断裂线位置的窄煤柱合理宽度的确定[J];采矿与安全工程学报;2014年01期
7 廖学东;黄飞;何廷峻;;近距离煤层群上行开采相似材料模拟试验研究[J];煤炭科学技术;2013年02期
8 吴林梓;王红胜;李树刚;董永建;;孤岛综放面区段煤柱优化及围岩控制技术[J];煤矿安全;2013年01期
9 张宏伟;韩军;海立鑫;李明;乔鸿波;;近距煤层群上行开采技术研究[J];采矿与安全工程学报;2013年01期
10 王成;张农;李桂臣;许兴亮;钱德雨;张念超;;上行开采顶板不同区域巷道稳定性控制原理[J];中国矿业大学学报;2012年04期
相关博士学位论文 前2条
1 王红胜;沿空巷道窄帮蠕变特性及其稳定性控制技术研究[D];中国矿业大学;2011年
2 冯国瑞;残采区上行开采基础理论及应用研究[D];太原理工大学;2009年
相关硕士学位论文 前2条
1 双海清;综放沿空掘巷围岩稳定性分析与控制技术研究[D];西安科技大学;2015年
2 吴林梓;基本顶断裂结构影响窄煤柱稳定性研究及工程应用[D];西安科技大学;2014年