金塘木岙物流区围填海工程通过竣工验收

发布时间:2018-02-22 01:57

  本文关键词: 木岙 竣工验收 物流区 金塘 水运规划 吹填砂 围堤 竣工决算 堤身 填海工程  出处:《水运工程》2017年02期  论文类型:期刊论文


【摘要】:正由中交水运规划设计院有限公司(水规院)设计的金塘木岙物流区围填海工程于2017年1月13日通过了竣工验收。本工程新建3 967 m护岸,其中西护岸(外护岸)2 560.8 m,北护岸148.2 m,内护岸1 258 m,吹填砂600.8万m3,陆域形成95.69万m2。工程财务竣工决算总投资10.24亿元。西护岸轴线位于-11.5 m水深附近,最深处堤身高度接近17 m,具有水深、潮流和波浪大等特点;围堤断面的宽度既关系到结构
[Abstract]:The reclamation project of Jintang Mu'ao Logistics area, which is being designed by Zhongjiao Water Transportation Planning and Design Institute Limited (Water Planning Institute), passed the completion acceptance on January 13th 2017. The new 3 967m bank revetment was built in this project. Among them, west bank protection (external bank protection 2 560.8 m, north bank protection 148.2 m, inner bank protection 1 258 m, sand filling six million eight thousand m 3, land area forming 956,900 m 2. The total investment of the financial final account of the project is one billion twenty-four million yuan. The west bank protection axis is located near -11.5 m water depth. The height of the deepest embankment is close to 17m, which has the characteristics of deep water, large tide and wave, etc. The width of the section of the embankment is related to the structure
【分类号】:U655.5

【相似文献】

相关重要报纸文章 前1条

1 曲直;柔中有刚不失为维稳良策[N];舟山日报;2012年



本文编号:1523373

资料下载
论文发表

本文链接:https://www.wllwen.com/guanlilunwen/wuliuguanlilunwen/1523373.html


Copyright(c)文论论文网All Rights Reserved | 网站地图 |

版权申明:资料由用户85fe9***提供,本站仅收录摘要或目录,作者需要删除请E-mail邮箱bigeng88@qq.com