港珠澳大桥沉管浮运安装计划与控制研究
[Abstract]:The sinking tunnel of Hongkong-Zhuhai-Macao Bridge is the first deep buried tunnel under construction in China. There are 33 submersible pipes and 1 final joint. The contract period is 36 months. The installation of sinking pipe floating is a control project of immersed pipe tunnel. In order to complete the contract period, the average speed of 1 knots / month is required for installation. However, the installation procedure of sinking pipe floating is many, demanding and difficult. And it must be carried out under a specific operation window, so it is difficult to control the installation schedule of sinking pipe floating. As the first offshore immersed tube tunnel in China, there is no successful experience in schedule control. How to use limited resources to complete the floating installation of sinking pipe within the contract period is the key and difficulty of project management. This paper is under this background to carry out the research. In this paper, using network planning technology, the construction progress chart of floating installation of sinking pipe of Hongkong-Zhuhai-Macao Bridge is compiled, resources are allocated, control program, methods and measures are put forward, and the theoretical results are applied to the practice of installation of sinking pipe, and the plan is adjusted. The specific work to be carried out is as follows: 1. Starting with the contract period, this paper analyzes the characteristics and difficulties of the floating installation of sinking pipe, formulates the overall goal and progress goal, and makes the schedule plan. First of all, decomposing the operation tasks of floating transportation and installation of sinking pipes, estimating the duration of each task, studying the logical relationship, importance, resource consumption, risk grade and other control conditions of each task, Based on this, a set of construction schedule control plan is worked out. Then the network technology is used to adjust and optimize the construction schedule, and a set of construction schedule. 2. 2. According to the construction schedule, the research on the floating installation resources of sinking pipes is carried out, and the ship machinery, personnel and materials needed for the project are configured, and the key and non-critical resources are identified. It is pointed out that the schedule. 3. 3 can be adjusted by adjusting the input of resources. The goal of schedule control is decomposed, and the control procedure, organization and control method of progress plan are worked out, and then the main measures of project schedule control are worked out. This paper applies the research theory to the practice of the floating installation of the sinking pipe of the HongKong-Zhuhai-Macao Bridge. According to the problems in the implementation of the plan, the reasons are analyzed, the improvement measures are formulated by the plan control method, and the subsequent construction schedule is adjusted. A new progress plan has been drawn up. It is pointed out in this paper that although there are 17 processes for the floating operation and installation of sinking pipes, the critical control work can be reduced to 4 by using the parallel working method using network planning technology. When the schedule is deviated, we can adjust the network plan, increase the resource input, strengthen the technical research, and strengthen the measures of organization guarantee.
【学位授予单位】:华南理工大学
【学位级别】:硕士
【学位授予年份】:2015
【分类号】:U459.5
【相似文献】
相关期刊论文 前10条
1 杨果;;港珠澳大桥应缓上马[J];中国水运;2006年05期
2 钟坚;;“港珠澳大桥”不如“深中大桥”[J];同舟共进;2007年07期
3 ;港珠澳大桥主体工程设计全球招标[J];建筑监督检测与造价;2008年11期
4 ;港珠澳大桥主体造价300多亿元[J];建筑监督检测与造价;2008年02期
5 晟华;;港珠澳大桥年内将启动招标[J];筑路机械与施工机械化;2008年03期
6 ;港珠澳大桥三方投资比例确定[J];公路;2008年03期
7 ;总投资422亿的港珠澳大桥已进入地质勘探阶段[J];新经济杂志;2008年03期
8 ;港珠澳大桥外业勘察通过验收[J];中外公路;2008年03期
9 ;港珠澳大桥有望年内开工[J];城市道桥与防洪;2009年02期
10 ;港珠澳大桥有望2009年底开工[J];施工技术;2009年03期
相关会议论文 前10条
1 ;港珠澳大桥终于通过论证确定[A];中国物流与采购联合会会员通讯总第33期-52期(2003年2月-12月)[C];2003年
2 柴建峰;陈晓东;孟凡超;程新生;孙连合;羊小云;李友龙;李学文;万仁凯;;港珠澳大桥主体工程初勘工作介绍[A];2010年全国工程地质学术年会暨“工程地质与海西建设”学术大会论文集[C];2010年
3 董润润;刘武君;彭为;;港珠澳大桥珠海口岸开发资金平衡分析[A];2012管理创新、智能科技与经济发展研讨会论文集[C];2012年
4 张东斌;;港珠澳大桥岛隧工程钢筋自动化加工技术[A];中国建筑学会建筑施工分会、中国工程机械工业协会施工机械化分会2012年会暨机械化施工新技术经验交流会会刊[C];2012年
5 郑定宁;;港珠澳大桥规模及规划概况[A];第十九届全国桥梁学术会议论文集(上册)[C];2010年
6 王驰;徐群;王学兰;;港珠澳大桥整体物理模型试验管理研究[A];第十六届中国海洋(岸)工程学术讨论会(下册)[C];2013年
7 刘晓东;;港珠澳大桥总体设计与技术挑战[A];第十五届中国海洋(岸)工程学术讨论会论文集(上)[C];2011年
8 陈洋洋;谭平;周福霖;陈树辉;;港珠澳大桥隔震方案的非线性动力学分析[A];第十四届全国非线性振动暨第十一届全国非线性动力学和运动稳定性学术会议摘要集与会议议程[C];2013年
9 李步恩;邱辉元;;港珠澳大桥岛隧工程西人工岛隧道防水施工技术[A];防水堵漏材料及施工技术交流会论文集[C];2014年
10 孟凡超;刘晓东;徐国平;;港珠澳大桥主体工程总体设计[A];第十九届全国桥梁学术会议论文集(上册)[C];2010年
相关重要报纸文章 前10条
1 记者 任春;港珠澳大桥专责小组成立[N];中国改革报;2007年
2 杨兴云;深中大桥立项在即港珠澳大桥恐添变数[N];经济观察报;2006年
3 本报记者 杨兴云;三地政府两套方案 港珠澳大桥融资难题待解[N];经济观察报;2007年
4 杨兴云;深中大桥立项在即 港珠澳大桥添变数[N];经理日报;2006年
5 本报记者 鲁宓;港珠澳大桥缘何迟迟未动工[N];亚太经济时报;2006年
6 记者 赵民望;“三地三检”破港珠澳大桥难题[N];中华工商时报;2006年
7 发文;港珠澳大桥专责小组成立并召开第一次会议[N];中华建筑报;2007年
8 郑晓波;港珠澳大桥建设加速启动[N];证券时报;2007年
9 刘和平;港珠澳大桥融资要有新思路[N];第一财经日报;2007年
10 本报记者 杜娟邋饶贞 骆建基 刘海健;港珠澳大桥最迟后年开工[N];广州日报;2008年
相关硕士学位论文 前10条
1 温忠宝;港珠澳大桥CB04标段钢箱梁吊具结构设计及有限元分析[D];大连交通大学;2015年
2 陈林;精细化管理在港珠澳大桥岛隧工程项目的应用[D];华南理工大学;2015年
3 王会雄;港珠澳大桥沉管浮运安装计划与控制研究[D];华南理工大学;2015年
4 张阳;港珠澳大桥珠海落脚点交通一体化—道路规划的初步研究[D];天津大学;2010年
5 冼超文;港珠澳大桥对珠海市产业政策发展的影响及优化研究[D];吉林大学;2013年
6 刘洹宇;港珠澳大桥对区域发展及交通运输的影响分析研究[D];华南理工大学;2010年
7 李庆喜;港珠澳大桥CB04标段131号墩台吊装结构设计及分析[D];大连交通大学;2014年
8 王艳珍;港珠澳大桥沉管隧道干坞坞址方案比选与环境影响研究[D];天津大学;2013年
9 汤召志;港珠澳大桥沉管隧道运营通风节能技术研究[D];西南交通大学;2012年
10 孙伟;港珠澳大桥主塔塔身结构模块化吊装有限元分析[D];大连交通大学;2014年
,本文编号:2259489
本文链接:https://www.wllwen.com/guanlilunwen/xiangmuguanli/2259489.html