世纪花园施工组织设计进度优化研究
本文选题:建筑工程 切入点:施工进度 出处:《西南科技大学》2017年硕士论文 论文类型:学位论文
【摘要】:工程项目的建设周期持续时间的长短决定了工程工期的在时间上独有的特性,对工程的工期计划进行优化改良必须切实有效地加强工程项目在进度方面的控制和管理,科学合理的进度计划安排对工程项目进度的进程管理起到了至关重要的作用。本文以世纪花园项目施工进度计划编制及优化改进实践为研究对象,通过参考国内外项目的进度管理现状和梳理各类文献,专业书籍中工程进度计划优化的基本原理,对其施工进度计划编制的结构分解、工序确定、时间计算、计划编制和时间参数计算过程进行详细的介绍和剖析,开展了针对进度计划的详细优化工作,对该方案的实际优化的效果进行了详细的分析,对该方案中出现的盲目压缩工期、资源冲突等问题的原因进行了剖析和反思,提出了例如科学合理压缩工期、资源平衡配置安排、提高人员素质、加强管理培训等有效的改进措施与建议,期望以此来大幅度提高工程进度方案管理控制的有效性。科学有效的施工组织设计方案可以使工程建设实现速度快、质量优、成本低的目标,在激烈的竞争中取得有利的位置。网络工程规划管理关键是流程之间的逻辑关系,并准确计算出精确的网络图表达不同的时间设置。要通过网络计划合理调整施工设计方案,压缩关键路径上的时间可以有效地缩短工期,而且费用可以适当调整。时间上的科学有序不能能顺利引导施工,还能减少在施工过程中遇到的问题的数量,以保证施工的顺利完成。
[Abstract]:The duration of the construction period of the project determines the unique characteristics of the construction period. The optimization and improvement of the project duration plan must effectively strengthen the control and management of the progress of the project. The scientific and reasonable schedule arrangement plays an important role in the process management of the progress of the project. This paper focuses on the preparation of the construction schedule of the Century Garden Project and the optimization and improvement of the project. By referring to the status quo of project schedule management at home and abroad and combing the basic principles of engineering schedule optimization in professional books, the structure decomposition, working procedure determination, time calculation of the construction progress plan are analyzed. The process of planning and time parameter calculation is introduced and analyzed in detail. The detailed optimization work for schedule is carried out. The effect of practical optimization of this scheme is analyzed in detail. This paper analyzes and reflects on the causes of resource conflict, and puts forward some effective improvement measures and suggestions, such as scientific and reasonable reduction of time limit, arrangement of balanced allocation of resources, improvement of personnel quality, strengthening of management training, etc. It is expected that the effectiveness of project schedule management and control can be greatly improved. A scientific and effective construction organization design scheme can make the project achieve the goals of high speed, excellent quality and low cost. The key to network engineering planning and management is the logical relationship between the processes, and accurately calculate the exact network diagram to express different time settings. The construction design scheme should be adjusted reasonably through the network plan. Shortening the time on the critical path can effectively shorten the construction period, and the cost can be adjusted appropriately. The scientific and orderly time can not guide the construction smoothly, and can also reduce the number of problems encountered in the construction process. To ensure the smooth completion of the construction.
【学位授予单位】:西南科技大学
【学位级别】:硕士
【学位授予年份】:2017
【分类号】:TU722
【参考文献】
相关期刊论文 前10条
1 刘阳;魏强;;浅析建筑工程管理中存在的问题及规范化措施[J];技术与市场;2016年01期
2 陈忠强;;网络计划技术在建设工程中的应用[J];中国新技术新产品;2010年01期
3 许晓芳;肖元真;吴泉国;;我国建筑业发展前景预测和对策措施[J];上海市经济管理干部学院学报;2009年04期
4 闻刚;王承蛟;李忠;李颖;;施工组织设计的作用和编制原则[J];辽宁建材;2009年04期
5 孟令树;;优化施工组织设计 合理确定工程造价[J];海河水利;2009年02期
6 王作成;;浅论施工组织设计编制方法的改进[J];黑龙江科技信息;2008年33期
7 唐江明;叶宏志;;浅谈施工组织设计的重要性[J];山西建筑;2008年23期
8 李实;余占环;丁志斌;;我国工程项目管理的发展现状及存在的问题[J];山西建筑;2008年08期
9 杨耀红;汪应洛;王能民;;工程项目工期成本质量模糊均衡优化研究[J];系统工程理论与实践;2006年07期
10 杨林生,钟才根,何锡兴;工程建设项目代建制的现状与发展问题[J];建设监理;2005年01期
相关硕士学位论文 前4条
1 杨斌;黑龙江移动LTE接入工程项目进度计划与控制研究[D];吉林大学;2014年
2 崔伟;安徽移动淮南分公司网优工程项目的进度管理研究[D];南京邮电大学;2013年
3 李敏;资源约束下多项目调度问题遗传算法研究[D];浙江大学;2008年
4 黄玉刚;施工组织设计对建设工程项目成本的影响研究[D];中南大学;2007年
,本文编号:1562981
本文链接:https://www.wllwen.com/jianzhugongchenglunwen/1562981.html