基于模糊综合评价法的综合单价风险量化
发布时间:2018-09-19 06:45
【摘要】:自实行工程量清单计价模式以来,投标人的报价风险费用隐含在工程量清单的综合单价中,综合单价的合理确定显得尤为重要。本文根据综合单价的组成对综合单价的风险因素进行了分析,将三角模糊数引入层次分析法中构建风险因素的判断矩阵,求出风险因素的权重,利用模糊综合评价的方法求出风险费用系数,根据投标人的预期利润率得到综合单价的综合风险系数。结合南京市某保障房项目对建立的模型进行算例分析,确定出符合项目特点和投标人实力的综合单价的综合风险系数。
[Abstract]:Since the implementation of the bill of quantities pricing model, the bidder's quotation risk cost is implied in the comprehensive unit price of the bill of quantities, and the reasonable determination of the comprehensive unit price is particularly important. In this paper, the risk factors of comprehensive unit price are analyzed according to the composition of comprehensive unit price. The triangular fuzzy number is introduced into AHP to construct the judgment matrix of risk factor, and the weight of risk factor is obtained. The risk cost coefficient is calculated by using fuzzy comprehensive evaluation method, and the comprehensive risk coefficient of the comprehensive unit price is obtained according to the expected profit rate of the bidder. Combined with an example of a indemnificatory apartment project in Nanjing, the comprehensive risk coefficient of the comprehensive unit price, which accords with the characteristics of the project and the strength of the bidder, is determined.
【作者单位】: 南京林业大学土木工程学院;
【分类号】:TU723.3
本文编号:2249350
[Abstract]:Since the implementation of the bill of quantities pricing model, the bidder's quotation risk cost is implied in the comprehensive unit price of the bill of quantities, and the reasonable determination of the comprehensive unit price is particularly important. In this paper, the risk factors of comprehensive unit price are analyzed according to the composition of comprehensive unit price. The triangular fuzzy number is introduced into AHP to construct the judgment matrix of risk factor, and the weight of risk factor is obtained. The risk cost coefficient is calculated by using fuzzy comprehensive evaluation method, and the comprehensive risk coefficient of the comprehensive unit price is obtained according to the expected profit rate of the bidder. Combined with an example of a indemnificatory apartment project in Nanjing, the comprehensive risk coefficient of the comprehensive unit price, which accords with the characteristics of the project and the strength of the bidder, is determined.
【作者单位】: 南京林业大学土木工程学院;
【分类号】:TU723.3
【相似文献】
相关期刊论文 前4条
1 霍如路;;谈综合单价的编制及应用[J];山西建筑;2014年12期
2 董文菊;从综合单价内涵分析施工项目风险管理[J];建材技术与应用;2005年03期
3 杨慧琴;;工程量清单计价中综合单价的分析与计算[J];门窗;2014年06期
4 贾广胜;;浅谈建筑电气工程审计中的几点体会[J];建筑监督检测与造价;2010年04期
相关硕士学位论文 前3条
1 刘云云;基于云计算Hadoop平台的综合单价预测研究[D];西安建筑科技大学;2016年
2 谭紫;风险控制下工程变更的方案优选及综合单价确定研究[D];安徽工业大学;2015年
3 王耀萱;建筑业营改增对建设工程造价的影响研究[D];西华大学;2016年
,本文编号:2249350
本文链接:https://www.wllwen.com/jianzhugongchenglunwen/2249350.html