配电网架空线路施工进度控制方法及实证研究
[Abstract]:Power grid is an important infrastructure in urban modernization construction. Strong power grid provides a strong guarantee for the development of national economy. The scale of investment and construction of power grid is large and the coverage is wide. It will obtain enormous economic and social benefits to plan the construction of power grid reasonably and to control the construction project of power grid effectively. Otherwise, if the urban power network planning is unreasonable and the investment construction control is not in place, it will bring irreparable losses to the national economic construction and people's life. Project schedule control is an important link in project construction management, which plays an important role in the implementation and quality assurance of the whole project. As one of the important economic indicators to measure the level of project management, whether the project can bring its economic benefits into full play is closely related to whether the project can be delivered within a specified time. Therefore, it is necessary to do the project schedule management well. Based on the research of traditional project construction schedule control theory, this paper expatiates on the current situation and problems of construction schedule management of overhead transmission line project in distribution network, which is backward in solving the problem of management mechanism, combining the current situation of project management research at home and abroad, and on the basis of traditional project construction schedule control theory research. The project progress dynamic control and optimization consciousness is not high, the communication and coordination is not enough, and the necessity of key chain project management is highlighted. This paper takes "Li Ying 110kV distribution network overhead line construction project" as an example, based on the key chain project management, on the basis of careful analysis of the engineering characteristics, route path and construction scheme of the project, the paper takes "Li Ying 110kV distribution network overhead line construction project" as an example, based on the key chain project management. Based on the theory of critical chain, the WBS decomposition of construction project is carried out, and the critical path is determined. The 50% probability time of the most optimistic completion time is used as the working procedure time to reduce the safe time, the constraint bottleneck is analyzed, and the engineering key chain is determined by using the priority criterion of parallel algorithm. The size of buffer zone is determined by elastic coefficient method, and the project schedule is finally determined. Through the key chain method mentioned above, the progress of the project is controlled, by setting green, yellow and red areas in the buffer zone, through the project risk estimation, the project multi-layer management, the scheduling management, the performance appraisal of the project manager, etc. Control the progress of the project. Through the control management model constructed, the progress of the overhead line construction project of Li Ying 110 kV distribution network is controlled by using the key chain method, which provides the guarantee for the successful completion of the project. It is proved that it is feasible to use the key chain technology to control the project schedule in theory and practice, and it can be popularized and applied in other projects of the same type in the future.
【学位授予单位】:华北电力大学(北京)
【学位级别】:硕士
【学位授予年份】:2017
【分类号】:TM752
【参考文献】
相关期刊论文 前10条
1 王锡来;;项目管理过程中的进度控制[J];企业改革与管理;2016年20期
2 吴志军;;浅析施工项目进度控制方法及原理[J];建材与装饰;2016年12期
3 李俊亭;;关键链项目进度控制技术综合分析研究[J];工程管理学报;2015年06期
4 尤建新;秦云;;基于贝叶斯网络模型的关键链项目进度管理[J];同济大学学报(自然科学版);2015年10期
5 闫文周;刘振超;任格叶;;关键链的随机性及在工程项目工期优化中应用研究[J];西安建筑科技大学学报(自然科学版);2015年04期
6 徐远;朱文喜;;关键链技术在建设项目进度管理中的应用研究[J];企业技术开发;2015年22期
7 张蕾;;空气分离项目管理过程中的进度控制基础与要点[J];项目管理技术;2015年07期
8 王倩;;输变电工程项目进度管理——基于关键链理论[J];工程经济;2015年05期
9 陈刚;李建国;马小全;;基于关键链技术的国际石油钻机系统集成项目进度管理研究[J];项目管理技术;2015年04期
10 周正龙;董雄报;左园;;MIS开发项目进度管理的关键链识别研究[J];科技管理研究;2014年19期
相关硕士学位论文 前3条
1 耿子尧;蒙东电力公司开鲁风电项目进度管理优化研究[D];吉林大学;2016年
2 李春晖;迎泽110kV输变电工程项目进度管理研究[D];华北电力大学;2014年
3 朱志海;台山输变电工程项目进度管理系统信息化研究[D];华北电力大学(北京);2011年
,本文编号:2406395
本文链接:https://www.wllwen.com/kejilunwen/dianlidianqilunwen/2406395.html