田集电厂协调控制系统优化
发布时间:2018-06-01 18:38
本文选题:优化 + 协调 ; 参考:《华东电力》2014年12期
【摘要】:详细介绍了淮沪煤电田集电厂1、2号机组协调控制系统优化工作的主要工作内容和优化后的效果。项目团队通过几年持续的努力,使机组的控制系统涵盖了机、炉优化的成果,以及运行的要求,并最终使这两台机组的变负荷性能达到了电网和电厂均比较满意的效果。
[Abstract]:This paper introduces in detail the main work contents and the optimized results of the coordinated control system of Unit 1 and Unit 2 in Huaihu Coal Mine Power Plant. Through several years of continuous efforts, the project team makes the control system of the unit cover the results of machine, furnace optimization and operation requirements, and finally makes the load variation performance of the two units reach the satisfactory results of both the power grid and the power plant.
【作者单位】: 国网上海市电力公司电力科学研究院;安徽华电宿州发电有限公司;大唐淮南洛河发电厂;
【分类号】:TM621
,
本文编号:1965223
本文链接:https://www.wllwen.com/kejilunwen/dianlilw/1965223.html