当前位置:主页 > 科技论文 > 矿业工程论文 >

穿越富水砂层冻结斜井冻结壁变形规律研究

发布时间:2018-07-03 05:38

  本文选题:富水砂层 + 冻结斜井 ; 参考:《西安科技大学》2015年硕士论文


【摘要】:开展富水砂层冻结斜井冻结壁变形规律研究具有重要的工程应用价值。本文以袁大滩冻结斜井工程为依托,采用理论分析、有限元模拟和现场实测的方法对穿越富水砂层冻结斜井冻结壁变形规律进行研究。主要结论有:(1)将井筒分为浅埋和深埋两种情况,分别采用岩柱法和普氏理论对斜井冻结壁厚度进行设计,给出了在浅埋和深埋条件下斜井冻结壁计算公式,结合袁大滩冻结斜井工程现场实际情况,计算出袁大滩斜井冻结壁厚度:浅埋时冻结壁厚度分别为:顶板2.5m,两帮1m,底板0.5m;深埋时冻结壁厚度分别为:顶板4.88m,两帮3.6m,底板3.9m。(2)随着冻结壁空顶距离的增大,冻结壁在水平向的位移呈“竖向”圆弧状分布;冻结壁竖向位移由条带状分布逐渐变为“水平”圆弧状分布;对比有限元模拟和现场实测结果可知,富水砂层地区冻结斜井空顶距离为20m时,不仅能够保证冻结壁的安全稳定,还能减少施工循环,达到快速施工的目的。(3)根据袁大滩冻结斜井工程现场实测结果可知,冻结壁下沉量有如下关系:顶板沉降右帮1/2拱处左帮1/2拱处,且顶板沉降速率最大;埋深越大顶板沉降越大,而且随着迎头面向前推进冻结壁沉降速率也随之增大。(4)井筒开挖后工作面温度自下而上逐渐升高,过了中心点之后又逐渐降低,且开挖后工作面温度呈现先降低后升高的趋势。
[Abstract]:It is of great engineering application value to study the deformation law of frozen wall of frozen inclined well in water rich sand layer. Based on the frozen inclined shaft project of Yuan Da Tan, the deformation law of frozen wall of frozen inclined well crossing rich water sand layer is studied by means of theoretical analysis, finite element simulation and field measurement. The main conclusions are as follows: (1) the shaft is divided into shallow water. The thickness of the frozen wall of inclined well is designed by rock column method and prun theory, and the calculation formula of the freezing wall of inclined shaft in shallow and deep buried conditions is given. The frozen wall thickness of Yuanda beach is calculated by combining with the actual situation of the frozen inclined shaft in Yuanda beach. The thickness of the frozen wall of Yuanda beach is calculated in the shallow buried and deep buried conditions. The thickness of the frozen wall is 2.5m, respectively, when shallow buried. Two groups of 1m and floor 0.5m, the thickness of the frozen wall in deep buried is 4.88m, two 3.6m, and 3.9m. (2) in the floor, the horizontal displacement of the frozen wall is "vertical" circular arc, and the vertical displacement of the frozen wall is gradually changed from strip distribution to the "horizontal" circular arc, and the finite element simulation and the scene are compared. The measured results show that the air top distance of the frozen inclined shaft in the rich water sand layer is 20m, not only can ensure the safety and stability of the freezing wall, but also reduce the construction cycle and achieve the purpose of rapid construction. (3) according to the site measured results of the frozen slope project in Yuan Da beach, the settlement of the frozen wall has the following relation: the left side of the right side of the roof settlement at the right side of the 1/2 arch 1/2 The subsidence rate of the roof is the largest in the arch and the greater the depth of the roof, and the settlement rate of the frozen wall increases with the front facing forward. (4) the temperature of the working face increases gradually after the excavation of the shaft, and then gradually decreases after the center point, and the temperature of the working surface after the excavation decreases first and then then increases.
【学位授予单位】:西安科技大学
【学位级别】:硕士
【学位授予年份】:2015
【分类号】:TD325

【参考文献】

相关期刊论文 前10条

1 杨更社;屈永龙;奚家米;;白垩系地层煤矿立井冻结壁的力学特性及温度场研究[J];岩石力学与工程学报;2014年09期

2 王衍森;文凯;;深厚表土中冻结壁与井壁相互作用的数值分析[J];岩土工程学报;2014年06期

3 周盛全;陈海明;;白垩系地层深井冻结壁温度场分布规律[J];冰川冻土;2013年05期

4 张文;;我国冻结法凿井技术的现状与成就[J];建井技术;2012年03期

5 耿萍;晏启祥;何川;汪波;;隧道水平冻结施工过程的数值模拟[J];工程力学;2010年05期

6 崔广心;;深厚表土中圆筒形冻结壁和井壁的力学分析[J];煤炭科学技术;2008年10期

7 陈朝晖;;冻结凿井技术研究进展与存在的问题[J];建井技术;2007年03期

8 王衍森;黄家会;杨维好;任彦龙;宋雷;;特厚冲积层中冻结井外壁温度实测研究[J];中国矿业大学学报;2006年04期

9 李方政,楼根达,余志松,李小军;基于蠕变效应的穿越隧道冻结帷幕开挖与支护三维数值模拟[J];岩土力学;2005年S1期

10 张开顺,李炳胜,杨维好,王衍森,宋雷;井筒冻结壁径向位移规律计算研究[J];中国煤炭;2005年11期



本文编号:2092601

资料下载
论文发表

本文链接:https://www.wllwen.com/kejilunwen/kuangye/2092601.html


Copyright(c)文论论文网All Rights Reserved | 网站地图 |

版权申明:资料由用户c2363***提供,本站仅收录摘要或目录,作者需要删除请E-mail邮箱bigeng88@qq.com