龙滩水电厂7号机组转子磁极移位分析及处理工艺探讨
发布时间:2019-06-02 04:04
【摘要】:龙滩水电厂7号机组在调速器改造后进行了甩负荷试验,试验后发现机组转子大部分磁极发生移位。对转子磁极位移的原因进行简要分析,制定了相应的修复方案,探讨了相关处理工艺,并对机组的运行维护提出了合理化建议。
[Abstract]:The load rejection test of No. 7 unit in Longtan Hydropower Plant was carried out after the governor revamping. After the test, it was found that most of the magnetic poles of the rotor of the unit were shifted. This paper briefly analyzes the causes of rotor magnetic pole displacement, formulates the corresponding repair scheme, probes into the related treatment technology, and puts forward some reasonable suggestions for the operation and maintenance of the unit.
【作者单位】: 龙滩水电开发有限公司龙滩水力发电厂;
【分类号】:TV734
本文编号:2490820
[Abstract]:The load rejection test of No. 7 unit in Longtan Hydropower Plant was carried out after the governor revamping. After the test, it was found that most of the magnetic poles of the rotor of the unit were shifted. This paper briefly analyzes the causes of rotor magnetic pole displacement, formulates the corresponding repair scheme, probes into the related treatment technology, and puts forward some reasonable suggestions for the operation and maintenance of the unit.
【作者单位】: 龙滩水电开发有限公司龙滩水力发电厂;
【分类号】:TV734
【相似文献】
相关期刊论文 前10条
1 刘忠德;万安水电厂发电机转子磁极存在的问题与处理[J];江西电力;2002年05期
2 何松林;吴瑞清;;广蓄电厂5号机组转子磁极故障分析与更换方案[J];云南水力发电;2008年04期
3 春洪浩;二滩电站转子磁极绝缘问题浅谈[J];水电站机电技术;2000年04期
4 古文新;广东粤电长潭发电公司转子磁极改造[J];水电站机电技术;2005年02期
5 武斌;许小娟;;黄河沙坡头水力发电厂一号发电机组转子磁极烧损原因分析及更换方案[J];水电站机电技术;2011年06期
6 黄俊锋;;飞来峡灯泡贯流式发电机转子磁极改造技术[J];电工技术;2009年07期
7 李开顺;发电机转子磁极温度过高分析及处理[J];小水电;2000年02期
8 胡光;关于转子磁极绕组交流阻抗试验的探讨[J];水力发电;1988年10期
9 蔡庆永;发电机转子磁极安装的问题及处理[J];小水电;1999年04期
10 柴方光;程振伟;;50MW水轮发电机转子磁极异常情况分析[J];华电技术;2011年02期
相关会议论文 前1条
1 何松林;吴瑞清;;广蓄电厂5号机组转子磁极故障分析与更换方案[A];南方十三省(区、市)水力发电学会秘书长会议论文集[C];2010年
相关硕士学位论文 前1条
1 吴越;大型同步发电机气隙远程监测与分析[D];华中科技大学;2015年
,本文编号:2490820
本文链接:https://www.wllwen.com/kejilunwen/shuiwenshuili/2490820.html