当前位置:主页 > 管理论文 > 项目管理论文 >

珊溪水库工程施工管理

发布时间:2019-04-25 19:37
【摘要】::珊溪水库工程是目前国内在建的第二高坝。枢纽施工的特点是 :工期紧、强度大、干扰多、要求高、施工工艺复杂。由于施工中实施了项目管理中的计划管理、经济管理、设备管理、质量管理、安全管理和人员管理 ,组织合理、运作科学 ,用 32个月时间实现了 2 0 0 0年 5月按期下闸蓄水、6月 2 8日首台机组提前发电的目标 ,为高面板堆石坝施工积累了经验。
[Abstract]:Shanxi Reservoir Project is the second tallest dam under construction in China. The characteristics of hub construction are: time limit is tight, strength is big, interference is many, requirement is high, construction technology is complex. As a result of the implementation of project management in the planning management, economic management, equipment management, quality management, safety management and personnel management, reasonable organization, scientific operation, The water storage target of the lower gate in May, 2000 and the first unit on June 28, 2000 were achieved in 32 months. The experience has been accumulated for the construction of high face rockfill dam.
【作者单位】: 中国水利水电第十二工程局第二分局!浙江文成325304
【分类号】:TV5

【相似文献】

相关期刊论文 前10条

1 陈新乐;珊溪水库泄洪洞钢衬制作[J];水电站机电技术;1999年02期

2 林泽强;珊溪水库工程建设概要[J];水力发电;2000年10期

3 吴垂涛;优质高效建设珊溪水库工程[J];水力发电;2000年10期

4 陈泽鑫;珊溪水库工程施工管理[J];水力发电;2000年10期

5 陈振文;珊溪水库工程枢纽总布置[J];水力发电;2000年10期

6 徐跃明;珊溪水库泄洪洞设计[J];水力发电;2000年10期

7 应宁坚;珊溪水库面板堆石坝施工及其特点[J];水力发电;2000年10期

8 李中方;珊溪水库工程开挖爆破施工[J];水力发电;2000年10期

9 陈文明,周清水;珊溪混凝土面板堆石坝垫层料生产与填筑[J];水力发电;2000年10期

10 应宁坚,朱丽萍;珊溪水库面板堆石坝施工渡汛保护方案浅析[J];水力发电;2000年10期



本文编号:2465400

资料下载
论文发表

本文链接:https://www.wllwen.com/guanlilunwen/xiangmuguanli/2465400.html


Copyright(c)文论论文网All Rights Reserved | 网站地图 |

版权申明:资料由用户0bd2a***提供,本站仅收录摘要或目录,作者需要删除请E-mail邮箱bigeng88@qq.com