电站项目合同终止索赔方法研究
发布时间:2018-05-11 20:14
本文选题:电站项目 + 半途终止 ; 参考:《上海交通大学》2014年硕士论文
【摘要】:电力工业是国民经济的第一基础产业,电力工业的发展对促进国民经济的发展和社会进步起到了非常重要的作用。电力工业的发展离不开电力建设项目,但是电力建设项目因为其投资金额大、项目建设周期长、技术复杂、建设和施工制约因素多也历来被视为风险密集型项目。特别是近十几年来随着人们环保意识的不断提高,项目环保因素也逐渐成为电力项目建设的一个日益关键的制约因素,国内国外有不少电力建设项目因为环保因素在建设过程中被半途终止。由于电站项目投资较大、参与方众多、合同关系复杂,遭遇合同执行半途终止时,各参与方如何能够在有限的时间内形成一个完整的、合规的、合理的、具备可操作性的索赔方案,从而有利于多方尽快就索赔方案达成一致、从而尽可能减少自身利益损失就成了一个现实的课题。本文在某一真实项目的基础上对电站项目合同终止索赔方法进行了理论结合实际的研究,希望能够找到这一类电站项目合同终止索赔的一般适用的索赔方法,从而能对日益融入全球化贸易、走向国际化道路的中国企业在日后需要对海外工程项目遭遇半途终止进行索赔时能够稍微有所借鉴和帮助。文章首先介绍论文课题的研究背景和意义、研究内容和方法,然后在某一真实项目信息的基础上通过系统分析方法对整个索赔方案的形成过程做了具体分析和研究:先明确索赔方案的评价性指标和索赔方案的结构,再研究初步索赔方案的形成依据和形成过程,然后通过对初步索赔方案的分析得出优化的方向和措施,从而形成最终索赔方案。在对整个索赔方案的形成过程中,注意在实际案例的基础上进行理论分析和研究,得出一般适用的索赔方法:索赔首先明确索赔范围和索赔依据,确定索赔要素;然后按阶段、按类别、按性质准备相应的索赔方案并自始自终通过索赔方案的时效性、合理性、合规性和可操作性四大评价指标来不断评估和完善索赔方案。
[Abstract]:Electric power industry is the first basic industry of national economy. The development of electric power industry plays a very important role in promoting the development of national economy and social progress. The development of electric power industry is inseparable from the electric power construction project, but the electric power construction project is always regarded as a risk intensive project because of its large investment amount, long project construction period, complex technology and many construction and construction constraints. Especially in the past ten years, with the increasing awareness of environmental protection, the environmental protection factor of the project has gradually become an increasingly critical constraint factor in the construction of electric power projects. Many electric power construction projects at home and abroad have been terminated halfway through the construction process due to environmental protection factors. Because of the large investment of the power station project, the large number of participants and the complicated contract relationship, how can each participant form a complete, compliant and reasonable one in a limited time when the contract is terminated halfway through the execution of the contract? It is a practical problem to have an operational claim scheme, which is conducive to reaching an agreement on the claim scheme as soon as possible, thus minimizing the loss of its own interests as much as possible. On the basis of a real project, this paper makes a theoretical and practical study on the method of contract termination of a power station project, hoping to find a general method of claim for termination of contract in this kind of power plant project. Therefore, the Chinese enterprises which are increasingly integrated into the globalization trade and are on the way to internationalization can use for reference and help in the future when they need to end their claims on overseas engineering projects halfway through their journey. First of all, the paper introduces the research background and significance, research content and methods. Then, on the basis of a real project information, the paper makes a concrete analysis and study on the forming process of the whole claim scheme through the method of systematic analysis: firstly, it clarifies the evaluation index of the claim scheme and the structure of the claim scheme. Then it studies the basis and process of the preliminary claim scheme, and then obtains the optimized direction and measures through the analysis of the preliminary claim scheme, and then forms the final claim scheme. In the course of forming the entire claim programme, pay attention to theoretical analysis and study on the basis of actual cases and arrive at a generally applicable claim method: the claim first defines the scope of the claim and the basis of the claim, determines the elements of the claim, and then, by stages, According to category, according to the nature of the corresponding claims, and from beginning to end through the claim scheme effectiveness, rationality, compliance and maneuverability four evaluation indicators to continuously evaluate and improve the claim scheme.
【学位授予单位】:上海交通大学
【学位级别】:硕士
【学位授予年份】:2014
【分类号】:F426.61
【参考文献】
相关期刊论文 前2条
1 朱星宇;王秀芹;;国际工程项目管理费索赔研究[J];国际经济合作;2009年03期
2 李金海;;基于霍尔三维结构的项目管理集成化研究[J];河北工业大学学报;2008年04期
相关硕士学位论文 前1条
1 王瑞雪;工程项目索赔的运用探讨[D];四川大学;2006年
,本文编号:1875418
本文链接:https://www.wllwen.com/jingjilunwen/gongyejingjilunwen/1875418.html