基于风险分析和模糊专家系统的超高压基建工程不可预见费估算

发布时间:2018-03-19 21:06

  本文选题:风险分析 切入点:模糊专家系统 出处:《水电能源科学》2013年01期  论文类型:期刊论文


【摘要】:针对工程项目投资中采用现有的方法估算不可预见费存在的不足,以超高压基建工程为例,构建了不可预见费估算理论模型,分析了超高压基建工程实施过程中存在的风险,并对各风险进行分类筛选,进而确定风险等级,再利用模糊专家系统估算工程的不可预见费。算例应用结果表明,基于风险分析和模糊专家系统来估算超高压基建工程不可预见费用的方法可行、有效,且估算误差均在10%以内。
[Abstract]:In view of the shortcomings of using the existing methods to estimate the unforeseen cost in the investment of the project, taking the UHV capital construction project as an example, the theoretical model of the unforeseeable cost estimation is constructed, and the risks in the implementation process of the UHV capital construction project are analyzed. The risk is classified and screened, and the risk grade is determined, and then the unpredictable cost of the project is estimated by using the fuzzy expert system. The application results show that, Based on the risk analysis and fuzzy expert system, the method of estimating the unforeseen cost of UHV infrastructure project is feasible and effective, and the estimation error is less than 10%.
【作者单位】: 中国南方电网超高压输电公司广州局;华北电力大学能源与电力经济研究咨询中心;
【分类号】:TU271.1;F285

【参考文献】

相关期刊论文 前4条

1 郑亚林,黄德隆,郭健;Fuzzy推理的Mamdani算法[J];宝鸡文理学院学报(自然科学版);2001年03期

2 苏羽,赵海,苏威积,张晓丹;基于模糊专家系统的评估诊断方法[J];东北大学学报;2004年07期

3 张道国;耿庆申;王宁宁;;电网建设全过程造价变动的原因及控制措施[J];能源技术经济;2011年10期

4 吴钊,尹朝庆;模糊专家系统推理机设计[J];武汉化工学院学报;2003年01期

相关硕士学位论文 前1条

1 胡白雪;超高压及特高压输电线路的电磁环境研究[D];浙江大学;2006年

【共引文献】

相关期刊论文 前10条

1 牛荣;;基于.NET技术的棉花种植专家系统的设计[J];安徽农业科学;2008年08期

2 吴希让,吴国s,

本文编号:1636000


资料下载
论文发表

本文链接:https://www.wllwen.com/jingjilunwen/kuaiji/1636000.html


Copyright(c)文论论文网All Rights Reserved | 网站地图 |

版权申明:资料由用户0c386***提供,本站仅收录摘要或目录,作者需要删除请E-mail邮箱bigeng88@qq.com