高位收水冷却塔结构优化模拟分析
发布时间:2018-02-17 06:50
本文关键词: 高位收水冷却塔 数值模拟 挡水板 收水装置 出处:《汽轮机技术》2017年05期 论文类型:期刊论文
【摘要】:通过建立高位收水冷却塔内收水单元的三维数值模型,利用Fluent对其进行了数值模拟,分析了不同挡水板位置对单元内流场、水滴飘零损失以及高位收水冷却塔通风量的影响,模拟结果表明:当挡水板的角度为45°板长为0.2m时,塔通风量最大,0m/s条件下的塔通风量达到11 920kg/s,较不加挡水板时提高8.69%,证明此时的收水装置阻力最低,效果最佳。
[Abstract]:Through the establishment of a three-dimensional numerical model of the intake unit in a high water intake cooling tower, the numerical simulation of the unit is carried out by using Fluent. The effects of different water baffle positions on the flow field, droplet drift loss and ventilation of the high water intake cooling tower are analyzed. The simulation results show that when the angle of the baffle is 45 掳and the length of the plate is 0.2m, the ventilation capacity of the tower reaches 11 920 kg / s when the maximum ventilation capacity is 0 m / s, which is 8.69 kg / s higher than that without the baffle. It is proved that the water collecting device has the lowest resistance and the best effect.
【作者单位】: 华北电力大学电站设备状态监测与控制教育部重点实验室;
【基金】:中央高校基本科研业务费专项资金资助项目(12Q39) 河北省自然科学基金项目(E2012502016)
【分类号】:TM62
【相似文献】
相关期刊论文 前2条
1 杨志刚;沈丽莲;;加热器挡水板结构可靠性分析[J];电站辅机;2009年02期
2 曾伟;来宾电厂1号炉文丘里水膜除尘器技术改造[J];广西电力;2003年03期
,本文编号:1517472