白鹤滩水电站施工供水系统规划设计

发布时间:2019-05-18 23:12
【摘要】:白鹤滩水电站施工期供水系统建设是水电站工程建设最早开工的项目之一,根据当地水源特点选择取水构筑物是关键。本文重点阐述了根据不同水源特点选择不同取水方式及取水构筑物,保证了整个供水系统的取水能力和工程建设连续、顺利进行,同时也可为类似水电站供水系统取水构筑物的选择设计提拱参考。
[Abstract]:The construction of water supply system of Baihetan Hydropower Station during construction is one of the earliest projects to start construction of hydropower station, and it is the key to select water intake structure according to the characteristics of local water source. This paper focuses on the selection of different water intake methods and water intake structures according to the characteristics of different water sources, which ensures the continuous and smooth construction of the water intake capacity and engineering of the whole water supply system. At the same time, it can also be used as a reference for the selection and design of water intake structure of similar hydropower station water supply system.
【作者单位】: 长江三峡技术经济发展有限公司;
【分类号】:TV752;TV54

【相似文献】

相关期刊论文 前10条

1 张成稳;曾厅余;宗德孝;居志刚;;白鹤滩水电站建设期气象保障服务思考[J];云南大学学报(自然科学版);2012年S2期

2 张为民,徐建强,计金华;金沙江白鹤滩水电站工程建设时机的选择[J];水力发电;2003年06期

3 ;金沙江白鹤滩水电站开工[J];云南水力发电;2011年06期

4 周双超;;张楚汉院士称:白鹤滩水电站综合技术指标居世界前列[J];四川水力发电;2006年04期

5 ;白鹤滩水电站施工总布置规划复核报告通过审查[J];水利水电施工;2010年04期

6 金珍宏;;白鹤滩水电站运行期能耗指标计算分析[J];水利规划与设计;2013年04期

7 刘振中;黎细波;张婷;;半预制式界桩在白鹤滩水电站建设征地界桩测设中的应用[J];大坝与安全;2012年04期

8 于雷;;白鹤滩水电站明挖工程爆破降尘试验方案研究[J];科技与企业;2013年22期

9 金珍宏;;白鹤滩水电站施工期能耗量分析方法[J];水利水电技术;2012年11期

10 ;白鹤滩水电站圆筒形调压室开挖支护专题报告咨询会议在北京召开[J];四川水力发电;2013年02期

相关会议论文 前1条

1 陈钢;冯真秋;;白鹤滩水电站1000MW机组设计方案[A];大型水轮发电机组技术论文集[C];2008年

相关重要报纸文章 前10条

1 《金沙江报道》记者 周双超;白鹤滩水电站综合技术指标居世界前列[N];凉山日报(汉);2006年

2 陆林康 石兴普;白鹤滩水电站成为中国第二大水电站[N];凉山日报(汉);2007年

3 张天春;白鹤滩水电站筹建工作启动[N];云南日报;2008年

4 本报记者 宋e,