浯溪口碾压混凝土重力坝混凝土分区设计及施工
发布时间:2018-01-11 01:15
本文关键词:浯溪口碾压混凝土重力坝混凝土分区设计及施工 出处:《水力发电》2016年02期 论文类型:期刊论文
更多相关文章: 碾压混凝土重力坝 混凝土分区 配合比 浯溪口水利枢纽
【摘要】:对浯溪口水利枢纽工程碾压混凝土重力坝混凝土分区设计方案、施工阶段遇到的难题及其处理措施进行了总结和研究,结果表明该工程混凝土坝分区设计与施工方案大大减少了混凝土胶凝材料用量,提高了施工机械化程度,加快了施工进度,同时降低了工程造价,在保证工程质量安全的同时取得了较明显的经济效益,可为类似工程混凝土分区设计与施工提供参考。
[Abstract]:Partition design of roller compacted concrete gravity dam of WUXIKOU hydro project construction phase of concrete, problems encountered and treatment measures were summarized and studied, the result showed that the engineering design and construction of concrete dam zoning scheme greatly reduces the amount of cementitious materials of concrete, improve the degree of mechanization construction, accelerate the construction schedule, and reduce the the cost of the project, to ensure project quality and safety and achieved obvious economic benefits, which can provide reference for the design and construction of concrete partition of similar projects.
【作者单位】: 江西省水利规划设计研究院;南昌大学建筑工程学院;
【基金】:江西省水利科技计划项目(KT201533)
【分类号】:TV642
【正文快照】: 0引言据不完全统计,目前碾压混凝土重力坝(RCC)在国内外迅速发展[1-11],世界上20多个国家已经修建了200多座RCC坝,分布在寒带、热带的各种气候环境之中。其中第1座RCC坝是美国1982年建成的坝高52 m的Willow Creek重力坝,在建的最高的碾压混凝土重力坝为中国龙滩大坝[5-6],第一
【相似文献】
相关期刊论文 前8条
1 于海涛;;某遗址防火分区设计可行性论证[J];消防科学与技术;2011年04期
2 彭连臣;;建筑防火分区设计探析[J];工程建设与设计;2010年02期
3 任宏伟;;建筑防火分区设计中的若干问题探析[J];新西部(下半月);2010年04期
4 董爱民;;浅析建筑防火分区设计的要点[J];科技资讯;2013年22期
5 郑慧颖;;建筑防火分区设计探析[J];科技创新与应用;2013年08期
6 何李源;;AP1000核电机组辐射分区设计调整[J];辐射防护通讯;2013年02期
7 黄砚玲,韩旭里,陈雄飞,郁可,刘爱萍;大型数据库INFORMIX的分区设计技术[J];山东建材学院学报;1998年04期
8 ;[J];;年期
,本文编号:1407552
本文链接:https://www.wllwen.com/kejilunwen/shuiwenshuili/1407552.html