水电工程基于Navisworks的四维施工模拟规划研究

发布时间:2018-02-27 10:37

  本文关键词: 水电工程 施工组织设计 Navisworks 四维施工模拟 出处:《水力发电》2017年10期  论文类型:期刊论文


【摘要】:四维施工模拟是对三维施工总布置和施工总进度的有机整合,即在空间的基础上增加时间维度,使施工规划更趋真实。基于Navisworks软件开展了水电工程四维施工模拟规划研究,初步建立了沂蒙抽水蓄能电站地面工程四维施工模拟模型,真实地反映了该工程施工总布置与总进度的关系,为施工项目管理提供了有利保障。
[Abstract]:Four-dimensional construction simulation is an organic integration of three-dimensional construction layout and total construction schedule, that is, adding time dimension on the basis of space to make construction planning more realistic. Based on Navisworks software, the research on four-dimensional construction simulation planning of hydropower project is carried out. The four-dimensional construction simulation model of Yimeng pumped Storage Power Station is established, which reflects the relationship between the general layout and the overall schedule of the project and provides a favorable guarantee for the construction project management.
【作者单位】: 中国电建集团北京勘测设计研究院有限公司;
【分类号】:TV52


本文编号:1542312

资料下载
论文发表

本文链接:https://www.wllwen.com/kejilunwen/shuiwenshuili/1542312.html


Copyright(c)文论论文网All Rights Reserved | 网站地图 |

版权申明:资料由用户5bb30***提供,本站仅收录摘要或目录,作者需要删除请E-mail邮箱bigeng88@qq.com