某水电站尾水渠体型优化试验研究
本文选题:尾水渠 + 模型试验 ; 参考:《水电能源科学》2016年09期
【摘要】:拟建的某水电站考虑充分利用发电水头,开挖下游汇口导致尾水渠出口河段水位整体降低,并因此造成尾水渠体型的不足。对此,以该水电站尾水渠体型为例,采用模型试验方法,从流态衔接、充分利用水头及防沙安全三方面对其进行体型优化研究。试验结果表明,当尾水渠出口高程调整至1 848.0m后,在该水电站常年运行工况下,各项参数均能达到相对最优。
[Abstract]:A planned hydropower station taking full advantage of power head, the downstream entrance leads to the tailrace excavation of the river water level to reduce the overall export, and thus causing the lack of tailrace shape. In this regard, the hydropower station tailrace type as an example, the model test method, from the pattern of convergence, make full use of sand and water head shape optimization of its safety. The experimental results show that when adjusting the tailrace outlet elevation to 1 848.0m, in the hydropower station year-round operation conditions, the parameters can be achieved relatively optimal.
【作者单位】: 四川大学水力学与山区河流开发保护国家重点实验室水利水电学院;四川省水利水电勘测设计研究院;
【分类号】:TV732
【参考文献】
相关期刊论文 前4条
1 王二平;朱瑞平;张欣;;某水电站工程尾水渠扩散段水力优化研究[J];华北水利水电大学学报(自然科学版);2015年01期
2 胥慧;王新;魏小旺;;尾水渠出流的数值模拟及体型优化[J];水电能源科学;2013年02期
3 尹崇清;周家俞;段金曦;吴门伍;;电站尾水渠水流条件试验研究[J];中国水运(下半月);2008年02期
4 彭勇;张建民;许唯临;;宽浅式尾水渠体型设计[J];长江科学院院报;2007年04期
【共引文献】
相关期刊论文 前5条
1 李峰;雷明慧;马旭东;聂锐华;;某水电站尾水渠体型优化试验研究[J];水电能源科学;2016年09期
2 冯雁敏;赵连辉;梁年生;;基于水位指数计算的下游不稳定流对水电站优化调度的影响[J];华北水利水电大学学报(自然科学版);2015年06期
3 黄明红;殷娟;;赣江石虎塘航电枢纽工程设计优化与验证[J];广东水利水电;2015年11期
4 童文辉;田业军;;航电枢纽布置与建筑物的设计方法[J];珠江水运;2015年11期
5 凌春海;;石虎塘航电枢纽布置及建筑物设计[J];广东水利水电;2014年01期
【二级参考文献】
相关期刊论文 前10条
1 孙东坡;李林昊;赵宝帅;李明佳;王宏飞;杨晓;;明渠扩散段急流运动特性及调控方法研究综述[J];华北水利水电大学学报(自然科学版);2014年04期
2 李逸凡;马秀媛;,
本文编号:1744484
本文链接:https://www.wllwen.com/kejilunwen/shuiwenshuili/1744484.html