当前位置:主页 > 科技论文 > 水利工程论文 >

丰满水电站重建工程高水头地下洞室群封堵设计

发布时间:2018-06-12 05:14

  本文选题:高水头 + 人工洞室群 ; 参考:《水利水电技术》2016年06期


【摘要】:正1工程概况丰满水电站全面治理(重建)工程是按恢复电站原任务和功能,在原丰满大坝下游120 m处新建一座大坝,并利用原丰满三期工程。工程以发电为主,兼有防洪、灌溉、城市及工业供水、养殖和旅游等综合利用。电站枢纽建筑物主要由碾压混凝土重力坝、坝身泄洪系统、左岸泄洪兼导流洞、坝后式引水发电系统、过鱼设施及利用的原三期电站组成。左岸泄洪兼导流洞前期作为导流泄水建筑物使用,工程施
[Abstract]:General situation of Zheng-1 Project Fengman Hydropower Station Comprehensive Control (Reconstruction) Project is to build a new dam at 120m downstream of the original Fengman Dam according to the original tasks and functions of the power station and utilize the original Fengman Phase III project. The main project is power generation, with comprehensive utilization of flood control, irrigation, urban and industrial water supply, aquaculture and tourism. The main building of the power station is composed of roller compacted concrete gravity dam, dam body flood discharge system, left bank flood discharge and diversion tunnel, back dam type water diversion power generation system, fish crossing facilities and the original third stage power station. The left bank flood discharge and diversion tunnel is used as the diversion and discharge structure in the early stage of the tunnel.
【作者单位】: 中水东北勘测设计研究有限责任公司;丰满大坝重建工程建设局;
【分类号】:TV738

【相似文献】

相关期刊论文 前10条

1 ;我国第二高水头电站元江依萨河电站建成投产[J];云南水力发电;1994年01期

2 张恩博;王千;常洪军;;丰满电厂3号机组高水头下稳定性试验研究[J];东北电力技术;2007年09期

3 江树R,

本文编号:2008510