溧蓄电站堆石坝碾压激振力实时监控及振动压实质量评估研究
[Abstract]:Effective control of the quality of dam filling roller compaction is the key to ensure the long-term safe and stable operation of Li-Li rockfill dam, and the roller compaction parameters (rolling speed, exciting force) are used in dam filling process. The number of compaction times and compaction thickness are the important factors affecting the compaction quality of dam body. The conventional method is to control the compaction quality of rockfill dam by using the methods of monitoring rolling parameters on the spot and random sampling of test points afterwards. On the one hand, the manual monitoring error is large, and the management is extensive. On the other hand, it is difficult to truly reflect the compaction of the whole construction silo with a limited number of test pit points. Based on the existing research in the laboratory, this paper deeply studies the real-time monitoring system of roller compaction excitation force of Li-Li rockfill dam, in order to realize the direct monitoring of the exciting force of roller compactor. At the same time, in order to overcome the one-sidedness of the finite number of test points reflecting the compaction of the whole construction silo surface and the time-consuming and laborious drawback of excavating the pit, the real-time evaluation method for the vibratory compaction quality of Li-Li rockfill dam is studied. In order to realize the rapid and comprehensive evaluation of the quality of rockfill dam roller compaction construction. The main contents and achievements of this paper are as follows: (1) the real time monitoring system of rolling excitation force of Li-Li rockfill dam is developed, the overall structure and function of the system are designed, and the monitoring and warning of the exciting force of roller compactor is realized. Combined with the field compaction, the application analysis was carried out. It provides a new technical means for directly controlling the exciting force of the roller and ensuring the exciting performance of the roller. (2) the real-time monitoring system for the vibratory compaction quality of the Li-li rockfill dam developed in the early stage of the laboratory is used. The monitoring value of compaction quality (CV) in the process of roller compaction construction is collected in real time. The BP neural network model for evaluating the dry density of vibratory compaction of Li-Li rockfill dam is established, and the spatial interpolation method is used. The compaction dry density at any point on the whole construction silo surface and the compaction dry density reached the standard rate of the whole construction silo surface can be obtained, and the rapid evaluation of the compaction quality in the construction area can be realized. It provides a reference for the quality control of filling roller compaction construction of Li-Li rockfill dam.
【学位授予单位】:天津大学
【学位级别】:硕士
【学位授予年份】:2014
【分类号】:TV641.4;TV698.1
【参考文献】
相关期刊论文 前10条
1 宁永升;;溧阳抽水蓄能电站上水库面板堆石坝关键技术研究[J];水力发电;2013年11期
2 宁永升;胡育林;胡旺兴;胡林江;;溧阳抽水蓄能电站枢纽布置设计[J];水力发电;2013年03期
3 马洪琪;钟登华;张宗亮;孙玉军;刘东海;;重大水利水电工程施工实时控制关键技术及其工程应用[J];中国工程科学;2011年12期
4 钟登华;刘东海;崔博;;高心墙堆石坝碾压质量实时监控技术及应用[J];中国科学:技术科学;2011年08期
5 ;Recent research and applications of GPS based technology for bridge health monitoring[J];Science China(Technological Sciences);2010年10期
6 ;Theoretical research on construction quality real-time monitoring and system integration of core rockfill dam[J];Science in China(Series E:Technological Sciences);2009年11期
7 黄悦照;;江苏宜兴抽水蓄能电站建设与管理[J];水力发电;2009年02期
8 徐泽平;邓刚;;高面板堆石坝的技术进展及超高面板堆石坝关键技术问题探讨[J];水利学报;2008年10期
9 李莉;胡建平;;克里金插值算法在等高线绘制中的应用[J];天津城市建设学院学报;2008年01期
10 吴晓铭;黄声享;;水布垭水电站大坝填筑碾压施工质量监控系统[J];水力发电;2008年03期
,本文编号:2126504
本文链接:https://www.wllwen.com/kejilunwen/shuiwenshuili/2126504.html