当前位置:主页 > 经济论文 > 经济管理论文 >

油田EPC项目物资采购风险点风险度综合评价研究

发布时间:2018-05-05 10:33

  本文选题:EPC + 采购 ; 参考:《西南石油大学》2014年硕士论文


【摘要】:EPC总承包模式是我国大力推广的一种建设工程总承包模式。近年,中国石油天然气集团公司明确提出,工程建设业务要突出、完善EPC总承包功能,积极推行先进的项目管理模式,努力提升市场竞争力。EPC总承包模式已成为油田工程建设主流模式。 油田的工程建设项目普遍具有工艺复杂、建设标准高等特点,且作业大多位于偏远地区,建设环境复杂,导致油田风险管理存在风险辨识困难,可靠性低,处理手段不够多样化等问题。 本文以EPC总承包模式及其风险的相关理论为基础,介绍了EPC模式的内涵、主要内容和特点,EPC项目风险的概念、产生机制和风险特点、分类。然后,本文从EPC项目物资采购的特点、流程着手,深入分析了采购准备阶段、采购实施阶段、采购完成后阶段的涉险环节,对主要风险点和风险源进行识别,建立了EPC项目物资采购风险体系,提出了风险度的衡量方法,构建了风险度乘积模型和模糊综合评价模型,给出风险度评价指标量化标准和风险度判别标准。 最后,本文结合TZ油田EPC项目案例,对项目总承包商物资采购环节中的主要风险进行分析识别,利用问卷调查法对风险点进行评价并排出顺序,提出了风险应对措施。另外,本文还针对该案例提出了一些建议供总承包商参考。
[Abstract]:EPC general contracting mode is one kind of construction project general contract mode that our country popularizes energetically. In recent years, CNPC has clearly proposed that the project construction business should be prominent, the overall contracting function of EPC should be improved, and advanced project management models should be actively implemented. EPC general contracting mode has become the main mode of oilfield engineering construction. The engineering construction projects in oil fields are generally characterized by complex technology and high construction standards, and most of the operations are located in remote areas, and the construction environment is complex, which leads to the difficulty of risk identification and low reliability in oil field risk management. To deal with the problem of not enough diversification of means and so on. Based on the general contracting mode of EPC and its risk theory, this paper introduces the connotation, main contents and characteristics of the EPC model, the concept of project risk, the mechanism and characteristics of the risk, and the classification of the risk. Then, this paper starts with the characteristics and flow of EPC project material procurement, deeply analyzes the risk links in the purchasing preparation stage, procurement implementation stage, procurement completion stage, and identifies the main risk points and risk sources. This paper establishes the risk system of EPC project material purchase, puts forward the measure method of risk degree, constructs the product model of risk degree and fuzzy comprehensive evaluation model, and gives the quantitative criterion of risk degree evaluation index and the criterion of risk degree discrimination. Finally, combined with the case of EPC project in TZ oilfield, this paper analyzes and identifies the main risks in the material procurement link of the general contractor of the project, evaluates the risk points by using the questionnaire method, and puts forward the measures to deal with the risks. In addition, this paper also puts forward some suggestions for the general contractor to refer to the case.
【学位授予单位】:西南石油大学
【学位级别】:硕士
【学位授予年份】:2014
【分类号】:F284;F251

【参考文献】

相关期刊论文 前10条

1 张根凤;;工程总承包项目风险要点分析与管理对策[J];重庆科技学院学报(社会科学版);2008年10期

2 杨会云;徐红玲;;模糊综合评价在EPC总承包投标风险中应用[J];低温建筑技术;2009年08期

3 周合亭;;EPC总承包工程中的设备采购管理探讨[J];经营管理者;2011年08期

4 马志刚;孙红艳;代德宇;;基于AHP的EPC管道工程项目风险识别与分析[J];国际石油经济;2012年08期

5 吕东军;;浅谈工程总承包项目的采购管理[J];安徽建筑;2012年04期

6 陈娟;;国际工程总承包风险及防范机制[J];上海经济研究;2008年05期

7 张凯天;石油化工工程总承包项目中的设备采购管理及其案例分析[J];炼油技术与工程;2005年10期

8 钟世威;马广庆;;企业标准化管理中存在的问题与对策[J];对外经贸;2012年07期

9 李路曦;王青娥;;基于供应链管理的EPC项目物资采购模式[J];科技进步与对策;2012年18期

10 朱毅;李吉勤;魏焱;李慧;南松;李小冬;;基于总承包商视角的EPC国际工程风险因素分级研究[J];工程管理学报;2012年05期

相关博士学位论文 前2条

1 李远远;基于粗糙集的指标体系构建及综合评价方法研究[D];武汉理工大学;2009年

2 王书吉;大型灌区节水改造项目综合后评价指标权重确定及评价方法研究[D];西安理工大学;2009年



本文编号:1847353

资料下载
论文发表

本文链接:https://www.wllwen.com/jingjilunwen/jingjiguanlilunwen/1847353.html


Copyright(c)文论论文网All Rights Reserved | 网站地图 |

版权申明:资料由用户e2951***提供,本站仅收录摘要或目录,作者需要删除请E-mail邮箱bigeng88@qq.com