盾构隧道管片位移因素分析及控制措施研究
本文关键词: 盾构隧道 管片位移 现场监测 数值模拟 出处:《西南交通大学》2015年硕士论文 论文类型:学位论文
【摘要】:本文以成都地铁某区间盾构隧道施工为工程背景,针对目前盾构法隧道施工过程中管片位移引起的错台问题,通过现场监测资料分析和数值模拟计算对管片错台和受力情况进行研究,分析错台影响因素并提出相应的控制措施。本文主要研究内容和成果如下:(1)根据现场监测资料分析管片错台沿隧道纵向的整体分布规律和盾构推进过程中随着管片至掌子面距离增大时错台的变化规律,结果表明管片错台整体上呈先增大后减小的趋势,并最终趋于稳定;管片脱出盾尾后在浮力作用下随着管片至掌子面距离的增大,错台随之增大并趋于稳定。(2)根据管片错台和盾构施工参数的现场监测资料,比较分析了各施工参数对管片错台的影响规律,依据分析结果提出了各施工参数的控制范围。(3)通过数值模拟分析了覆土厚度、千斤顶推力、注浆压力和螺栓预紧力对管片错台的影响,结果表明覆土厚度和注浆压力增大时管片错台随之增大,并且注浆压力分布方式对管片错台的分布位置影响很大;千斤顶推力和螺栓预紧力增大时管片错台随之减小。(4)根据现场监测资料分析和数值模拟计算的研究结果,分析总结了造成管片错台的影响因素,结合实际施工情况提出了管片位移控制措施。
[Abstract]:Based on the construction of shield tunnel in a section of Chengdu Metro, this paper aims at the problem of staggered platform caused by segment displacement during the construction of shield tunnel. Based on the field monitoring data analysis and numerical simulation, the staggered table and the stress of the segment are studied. This paper analyzes the influence factors of the wrong station and puts forward the corresponding control measures. The main contents and results of this paper are as follows: 1). According to the field monitoring data, the overall distribution law of segment stagger along the longitudinal tunnel and the variation law of stagger with the increase of the distance from segment to palm in shield tunneling process are analyzed. The results show that the segment stagger has a trend of first increasing and then decreasing, and finally tends to be stable. With the increase of the distance between the segment and the face of the shield, the stagger will increase and tend to be stable. (2) according to the field monitoring data of the construction parameters of the segmental staggered platform and shield tunneling, the segment is removed from the shield tail under the action of buoyancy. Based on the analysis results, the control range of each construction parameter is put forward. The thickness of overburden and the thrust of Jack are analyzed by numerical simulation. The effect of grouting pressure and bolt pre-tightening force on the stagger of segment is studied. The results show that the stagger increases with the increase of the thickness of soil and the grouting pressure, and the distribution mode of grouting pressure has a great influence on the distribution of the stagger. With the increase of Jack thrust and bolt pre-tightening force, the segment stagger is reduced. 4) based on the field monitoring data analysis and numerical simulation results, the influence factors of segment stagger are analyzed and summarized. Combined with the actual construction situation, the control measures of segment displacement are put forward.
【学位授予单位】:西南交通大学
【学位级别】:硕士
【学位授予年份】:2015
【分类号】:U455.43
【参考文献】
相关期刊论文 前10条
1 韩江龙;容继盘;;成型地铁隧道管片破损原因分析及处理措施[J];工程质量;2014年S2期
2 李旭;;地铁隧道混凝土管片的生产与裂缝控制研究[J];科技资讯;2014年35期
3 胡子丰;;浅析盾构施工管片破损原因和监督要点[J];安徽建筑;2014年05期
4 朱健;李刚;;地铁隧道管片破损修补新技术[J];城市道桥与防洪;2013年11期
5 王建;张琨玮;;盾构管片错缝拼装的一种简化计算有限元模型[J];四川建筑;2013年05期
6 蒋奇;付云升;;盾构选型与发展趋势[J];水利规划与设计;2013年03期
7 戴志仁;;盾构隧道盾尾管片上浮机理与控制[J];中国铁道科学;2013年01期
8 郑勇;;浅论隧道修建技术发展的趋势[J];广东科技;2012年11期
9 魏纲;洪杰;魏新江;;盾构隧道施工阶段管片上浮的力学分析[J];岩石力学与工程学报;2012年06期
10 李宇杰;何平;秦东平;;地铁盾构隧道管片受力分析[J];土木工程学报;2011年S2期
相关会议论文 前3条
1 谢玉杰;江华;;盾构推进中管片错台原因分析[A];2011中国盾构技术学术研讨会论文集[C];2011年
2 钟志全;;盾构管片错合分析及措施[A];施工机械化新技术交流会论文集(第七辑)[C];2006年
3 董志明;谭忠盛;洪开荣;;对施工过程中盾构隧道管片破损的有限元分析[A];中国土木工程学会第十一届、隧道及地下工程分会第十三届年会论文集[C];2004年
相关硕士学位论文 前4条
1 张鹏;地铁盾构隧道管片接头的理论分析及应用研究[D];北京交通大学;2011年
2 张强;盾构隧道通缝拼装管片的上浮和错台研究[D];上海交通大学;2007年
3 郑心铭;盾构隧道管片结构的理论研究及计算分析[D];西南交通大学;2005年
4 谢宗林;地铁区间盾构隧道管片衬砌结构力学行为的现场试验研究[D];西南交通大学;2004年
,本文编号:1471779
本文链接:https://www.wllwen.com/kejilunwen/daoluqiaoliang/1471779.html