张家界大峡谷玻璃桥基础设计
发布时间:2019-05-11 03:44
【摘要】:张家界大峡谷玻璃桥是一座主缆跨度430m的空间索面人行悬索桥。桥址位于喀斯特岩溶地貌区域,针对桥位处特殊的地形地貌和地质情况,东侧锚碇采用重力式锚,基础为明挖扩大基础(东南侧采用矩形扩大基础,东北侧采用阶梯式扩大基础);西侧锚碇采用锚塞体截面线性变化的隧道式锚,锚塞体长度为13.5m。桥塔塔柱均为圆环形钢筋混凝土独柱结构,每根塔柱均采用4根直径1.2m的人工挖孔灌注桩基础。桥墩采用桩柱式带盖梁的框架墩结构,每个墩柱下为直径1.5m的挖孔灌注桩。
[Abstract]:Zhangjiajie Grand Canyon Glass Bridge is a space cable pedestrian suspension bridge with a span of 430m. The bridge site is located in the Karst geomorphological area. In view of the special topographic, geomorphological and geological conditions at the bridge site, the gravity anchor is used in the east Anchorage, which is based on open excavation and expansion foundation (rectangular expansion foundation is used in the southeast side). On the northeast side, the stepped expansion foundation is adopted); The west side Anchorage adopts tunnel anchor with linear variation of anchor plug section, and the length of anchor plug body is 13.5 m. The tower columns of the bridge are circular reinforced concrete single column structures, and four artificial excavated cast-in-place pile foundations with a diameter of 1.2 m are used in each tower column. The pier adopts pile-column frame pier structure with cover beam, and each pier column is an excavated cast-in-place pile with a diameter of 1.5 m.
【作者单位】: 中铁大桥勘测设计院集团有限公司;
【分类号】:U448.25
[Abstract]:Zhangjiajie Grand Canyon Glass Bridge is a space cable pedestrian suspension bridge with a span of 430m. The bridge site is located in the Karst geomorphological area. In view of the special topographic, geomorphological and geological conditions at the bridge site, the gravity anchor is used in the east Anchorage, which is based on open excavation and expansion foundation (rectangular expansion foundation is used in the southeast side). On the northeast side, the stepped expansion foundation is adopted); The west side Anchorage adopts tunnel anchor with linear variation of anchor plug section, and the length of anchor plug body is 13.5 m. The tower columns of the bridge are circular reinforced concrete single column structures, and four artificial excavated cast-in-place pile foundations with a diameter of 1.2 m are used in each tower column. The pier adopts pile-column frame pier structure with cover beam, and each pier column is an excavated cast-in-place pile with a diameter of 1.5 m.
【作者单位】: 中铁大桥勘测设计院集团有限公司;
【分类号】:U448.25
【相似文献】
相关期刊论文 前10条
1 雷志辉;国道214线角笼坝大桥锚碇工程施工技术[J];世界桥梁;2005年02期
2 李家平,张子新,黄宏伟,李永盛;宁波庆丰大桥锚碇室内相似模型试验研究[J];同济大学学报(自然科学版);2005年08期
3 王宗仁,王崇旭,庄值政,谢明;四渡河桥隧道式锚碇开挖支护工艺[J];施工技术;2005年S1期
4 刘子振;王长征;言志信;;桩台式锚碇设计优化及应用[J];森林工程;2006年03期
5 张少军;;阳逻长江公路大桥南锚碇基础工程建设关键技术[J];世界桥梁;2006年02期
6 廖新;;大体积锚碇开挖施工探讨[J];科技咨询导报;2007年28期
7 白雪o,
本文编号:2474222
本文链接:https://www.wllwen.com/kejilunwen/daoluqiaoliang/2474222.html