具有非零F-S搭接时间任务的施工设备动态调度
发布时间:2018-03-28 13:57
本文选题:非零F-S搭接时间 切入点:施工调度 出处:《人民长江》2016年23期
【摘要】:针对工程施工过程中经常发生非零F-S搭接时间任务的设备调度问题,考虑任务间的搭接约束,引入标准时间任务、搭接时间任务和扩展任务工艺树概念,提出了一种将非零F-S搭接时间任务变换为紧密衔接任务的处理方法。根据调度任务批次,采用拟关键路径法和最佳适应调度法实现关键设备上的任务尽量紧凑执行的调度目标,开发出了一种具有非零F-S搭接时间任务的动态调度算法。工程案例应用表明:该调度算法能较好地解决非零F-S搭接时间的施工设备调度问题,而且能够扩展至动态紧密衔接任务的施工设备调度。
[Abstract]:In view of the equipment scheduling problem in which non-zero F-S lapping time tasks occur frequently in the construction process of engineering, the concept of standard time task, lap time task and extended task process tree is introduced, considering the overlap constraints between tasks. In this paper, a method of transforming non-zero F-S lapped time tasks into tightly connected tasks is proposed. According to the batch of scheduling tasks, the quasi-critical path method and the optimal adaptive scheduling method are used to realize the scheduling objectives of tasks on critical equipment that are as compact as possible. A dynamic scheduling algorithm with non-zero F-S lap time task is developed. The engineering case shows that the scheduling algorithm can solve the scheduling problem of construction equipment with non-zero F-S lap time. And can be extended to the dynamic tight connection of the construction equipment scheduling.
【作者单位】: 三峡大学水利与环境学院;三峡大学水电工程施工与管理重点实验室;
【分类号】:TV51
【相似文献】
相关期刊论文 前10条
1 李乾谅;;水电建设施工设备状况及主要问题分析[J];水利水电施工;1996年02期
2 杨明月,张富廷,刘岩;关于水利水电工程建设单位(业主)自有施工设备管理的若干探讨[J];江西水利科技;1998年03期
3 林占山,杨全万;施工设备的管理与使用[J];吉林水利;2002年09期
4 贺恭;加强施工设备管理保证三峡二期工程建设[J];建筑机械;1999年11期
5 韦桂生;;水利水电项目施工设备的管理及技术运用[J];技术与市场;2012年12期
6 王华;;浅析水利工程中施工设备的选择及管理[J];黑龙江科技信息;2014年20期
7 胡捷;;浅谈大型水电站建设期施工设备的运行管理[J];四川水力发电;2009年05期
8 内田清一;方爱珍;;当前大坝施工技术的发展和对施工设备的要求[J];人民长江;1979年01期
9 邢志勇;刘新录;刘兆河;张曰红;;浅谈机淤固堤工程施工设备发展趋势[J];科技促进发展;2010年S1期
10 贺恭;加强施工设备管理 保证二期工程建设[J];中国三峡建设;1999年09期
,本文编号:1676612
本文链接:https://www.wllwen.com/kejilunwen/shuiwenshuili/1676612.html