青岛市省道朱诸路祝沟河大桥抢修工程项目投资控制研究
发布时间:2018-03-12 18:05
本文选题:公路桥梁 切入点:抢修工程项目 出处:《中国海洋大学》2014年硕士论文 论文类型:学位论文
【摘要】:公路桥梁抢修工程项目是一类比较特殊的公路桥梁工程项目。在公路抢修工程项目实际组织实施的过程中,经常发生投资额超过批复预算的情况。所以,对公路桥梁抢修工程项目如何进行有效的投资控制具有非常重要的研究价值。本文通过综合借鉴国内外各种项目成本管理及投资控制的相关理论和实际做法,根据公路桥梁抢修工程项目的特点,针对青岛市省道朱诸路祝沟河大桥抢修工程项目,分析阐述该公路抢修工程项目投资控制的内容以及控制方法,即项目投资控制是按照一条纵线、一条横线两条线索来展开:一条纵线是指按工程推进过程来展开,由于公路抢修工程项目没有项目可行性研究阶段也没有招投标阶段,故大体可分为工程设计阶段和工程施工阶段,论文对这两个阶段的投资控制进行研究。一条横线指的是工程各阶段的不同参与方包括项目审批单位、建设单位、设计单位、施工单位等,论文根据各参与方由于不同的工作责任,而产生的对投资控制的不同角度和不同侧重点进行研究。论文通过纵线和横线的交叉,理清朱诸路祝沟河大桥抢修工程项目投资控制的完整脉络,找出影响投资的关键因素,并研究控制关键因素的具体做法,从而得出最终的结论。
[Abstract]:Highway bridge repair project is a kind of special highway bridge engineering project. In the process of actual organization and implementation of highway emergency repair project, the investment often exceeds the approved budget. How to carry on the effective investment control to the highway bridge urgent repair project has the very important research value. This article draws lessons from the domestic and foreign each kind of project cost management and the investment control related theory and the practice comprehensively, According to the characteristics of the emergency repair project of highway and bridge, aiming at the urgent repair project of Zhuzhulugou River Bridge of Qingdao provincial road, this paper analyzes and expounds the contents and control methods of the investment control of the highway emergency repair project. That is, the project investment control is carried out according to one vertical line, one horizontal line and two clues: one vertical line is carried out according to the progress of the project, because the highway rush repair project has no project feasibility study stage and no bidding stage. So it can be divided into engineering design stage and engineering construction stage, the paper studies the investment control of these two phases. A horizontal line refers to the different participants in each stage of the project including the project approval unit, the construction unit, the design unit, the project approval unit, the construction unit, the design unit, the project approval unit, the construction unit and the design unit. According to the different angles and emphases of investment control produced by the participants due to their different working responsibilities, the paper passes through the intersection of the vertical and horizontal lines. This paper clarifies the complete context of investment control of Zhu Zhu Lu Zhugou River Bridge rush repair project, finds out the key factors affecting investment, and studies the concrete methods of controlling key factors, and draws the final conclusion.
【学位授予单位】:中国海洋大学
【学位级别】:硕士
【学位授予年份】:2014
【分类号】:F283
【参考文献】
相关期刊论文 前10条
1 孙彬;李正中;王春梅;程棋锋;;基于流程管理特性的施工成本管控研究[J];公路;2013年03期
2 盛东兴;翟洪刚;;建设项目全过程跟踪审计在之江大桥工程中的应用[J];公路交通科技(应用技术版);2012年12期
3 柯洪;周付彦;;公路工程造价管理绩效评价指标体系研究[J];公路交通科技;2012年12期
4 覃正标;胡敏杰;;特许权限定模式对项目投资价值的影响——基于高速公路BOT的分析[J];财会通讯;2012年29期
5 陈伏冰;;公路工程新旧估算指标案例对比分析[J];中外公路;2012年05期
6 姚亚峰;唐正光;;设计阶段对投资控制的分析[J];公路;2012年09期
7 贾新红;;如何做好项目成本管理[J];公路;2012年06期
8 刘U,
本文编号:1602686
本文链接:https://www.wllwen.com/guanlilunwen/chengbenguanlilunwen/1602686.html