步步川110kV智能变电站项目全寿命周期成本管理研究
本文选题:智能变电站项目 + 全寿命周期 ; 参考:《华北电力大学(北京)》2017年硕士论文
【摘要】:我国的经济仍在不断发展,电力需求也仍在提高,电力建设投资额度仍然巨大。为了降低成本,提高收益,电力企业在进行电力工程项目管理时,往往注重了当前的低成本,即大力控制初始建设投资成本,而未考虑到后期包括运行检修、报废处理等阶段产生的费用,导致工程项目后期成本难以控制而偏高,工程项目全寿命周期成本也相应提高,不利于项目的可持续发展,也影响项目全寿命的投资收益。为了变电站工程项目的可持续发展,应从变电站项目的全寿命周期的角度,综合考虑从初始设计到最终报废的整个期间的成本,才能保证变电站项目其全寿命周期的投资收益。本文根据步步川110kV第二代智能变电站项目的实际基本情况,结合工程项目全寿命周期成本管理的相关理论研究;基于工程项目全寿命周期成本估算方法;以步步川110kV第二代智能变电站工程项目为具体研究对象,分析计算其全寿命周期成本,并对步步川智能变电站工程项目全寿命周期成本进行优化分析,主要阐述全寿命周期成本优化理论,指出全寿命周期成本优化各阶段的目标,论述如何对该项目进行成本优化。最后,本文对项目全寿命周期成本控制系统进行研究,着重阐述基于价值工程的全寿命周期成本控制方法,将技术和经济结合起来,保证质量的前提下,用最低的成本来实现智能变电站项目的价值。
[Abstract]:The economy of our country is still developing, the demand of electricity is still increasing, and the investment amount of electric power construction is still huge. In order to reduce the cost and increase the income, the electric power enterprises often pay attention to the current low cost, that is, to control the initial construction investment cost, but not to consider the later period, including the operation and maintenance, when the electric power enterprise carries on the electric power engineering project management. Due to the expense in the stage of scrap disposal, it is difficult to control the cost in the later stage of the project, and the cost of the whole life cycle of the project also increases accordingly, which is not conducive to the sustainable development of the project and affects the investment income of the whole life of the project. In order to maintain the sustainable development of substation project, the cost of the whole life cycle of substation project should be considered comprehensively from the point of view of the whole life cycle of substation project, so as to ensure the investment income of the whole life cycle of substation project. According to the actual situation of the second generation intelligent substation project of Chuanchuan 110kV, this paper studies the related theory of the whole life cycle cost management of the engineering project, based on the method of estimating the whole life cycle cost of the engineering project. Taking the second generation intelligent substation project of Sichuan 110kV as the concrete research object, the whole life cycle cost is analyzed and calculated, and the whole life cycle cost of the step by step Sichuan intelligent substation project is optimized and analyzed. This paper mainly expounds the theory of life cycle cost optimization, points out the goal of every stage of life cycle cost optimization, and discusses how to optimize the cost of the project. Finally, this paper studies the project life cycle cost control system, focusing on the cost control method based on value engineering, combining technology and economy to ensure quality. Realize the value of intelligent substation project with the lowest cost.
【学位授予单位】:华北电力大学(北京)
【学位级别】:硕士
【学位授予年份】:2017
【分类号】:TM63
【参考文献】
相关期刊论文 前10条
1 李存斌;庆格夫;陆龚曙;李鹏;;基于全生命周期成本的配电网变压器选型系统动力学模型[J];现代电力;2014年03期
2 李自怡;;火电厂目标成本管理研究[J];电网与清洁能源;2014年01期
3 李惠玲;李晓琴;刘航天;;建设工程造价指数的分析与预测[J];沈阳建筑大学学报(社会科学版);2013年01期
4 柳璐;王和杰;程浩忠;刘建琴;;基于全寿命周期成本的电力系统经济性评估方法[J];电力系统自动化;2012年15期
5 黄兴;;企业经济管理中的目标成本管理探究[J];现代经济信息;2012年15期
6 巴雅尔图;;我国企业实施作业成本管理现状及发展趋势分析[J];中国管理信息化;2012年09期
7 刘大鹏;;企业全面预算管理中作业成本法应用探讨[J];财会通讯;2012年11期
8 党江艳;;价值链分析在战略成本管理中应用的理论研究[J];价值工程;2012年09期
9 陈涛;;浅谈工程成本控制[J];科学之友;2011年21期
10 陈迈;吴霆声;王瑜;陈义忠;;电网企业作业成本管理的应用探讨[J];能源技术经济;2011年05期
相关博士学位论文 前1条
1 苏海锋;配电系统规划全寿命周期管理理论和方法研究[D];华北电力大学;2012年
相关硕士学位论文 前3条
1 曹胜楠;基于全寿命周期成本的配电网规划方案的评估[D];华北电力大学;2012年
2 张媛;基于灰色系统理论的电力设备全寿命周期成本评估及模型[D];重庆大学;2008年
3 彭莉;产品设计阶段的成本管理研究[D];武汉大学;2005年