辽宁龙源风电公司基本建设成本控制研究
发布时间:2018-11-05 16:21
【摘要】:2006年以来,随着国家一系列优惠政策的出台,我国风电行业得到了迅猛发展。目前,风电的千瓦造价大约是传统火电的两倍,这就意味着基本建设成本的高低对项目未来的盈利能力有着重要影响。辽宁龙源风电公司是2006年成立的,在大规模的工程建设过程中,公司在基建成本控制方面有经验也有不足,我们在工作过程中不断总结,使公司基建成本管理制度不断完善,公司基建成本控制水平不断提高。 本文共五个部分:第一章为绪论,阐述本文选题的背景和意义,介绍了国内外文献的论述,同时,对本文论述的主要内容做了说明。第二章是电力企业基本建设成本控制相关理论,介绍了电力企业基本建设成本控制的构成、特点及原则。第三章分析了辽宁龙源风电公司基本建设成本控制现状,介绍了辽宁龙源风电公司的基本情况,公司风电基本建设成本控制情况和在成本控制过程中出现的问题。第四章提出辽宁龙源风电公司基本建设成本控制改进与完善措施,就第三章中提到的成本控制过程中出现的问题提出了改进和完善的内容、方法和原则。第五章提出了改进与完善的预期效果分析,分析了改进和完善后达到的预期效果。最后是结论。 本论文以风电建设项目成本控制为研究对象,遵循项目成本控制理论,探寻风电建设项目成本控制的关键环节,通过分析影响成本的主要因素,探求建立风电项目成本控制的有效途径,以期能有助于风电建设项目成本的不断降低,促进风电行业健康发展。论文通过分析辽宁龙源风电场建设项目实例,运用分析比较、层次分析等方法,独立思考提出降低风电工程造价的措施,力求对提高风电工程整体的盈利能力有一定的借鉴作用。
[Abstract]:Since 2006, with the introduction of a series of preferential policies, wind power industry in China has developed rapidly. At present, the kilowatt cost of wind power is about twice that of traditional thermal power, which means that the level of capital construction cost has an important impact on the future profitability of the project. Liaoning Longyuan Wind Power Company was established in 2006. In the process of large-scale project construction, the company has both experience and deficiency in capital construction cost control. We continue to sum up in the course of our work, so that the company's capital construction cost management system is constantly improved. The company's capital construction cost control level continues to improve. There are five parts in this paper: the first chapter is the introduction, which describes the background and significance of this topic, introduces the domestic and foreign literature, and explains the main content of this paper. The second chapter is the related theory of power enterprise capital construction cost control, introduces the composition, characteristic and principle of power enterprise capital construction cost control. The third chapter analyzes the current situation of capital construction cost control of Liaoning Longyuan wind power company, introduces the basic situation of Liaoning Longyuan wind power company, the cost control of wind power capital construction of Liaoning Longyuan wind power company and the problems in the process of cost control. The fourth chapter puts forward the improvement and improvement measures of capital construction cost control of Liaoning Longyuan Wind Power Company, and puts forward the contents, methods and principles of improvement and perfection on the problems in the process of cost control mentioned in the third chapter. In the fifth chapter, the expected effect of improvement and perfection is analyzed, and the expected effect after improvement and perfection is analyzed. Finally is the conclusion. This paper takes the cost control of wind power construction project as the research object, follows the project cost control theory, explores the key link of the cost control of wind power construction project, and analyzes the main factors that affect the cost. This paper explores the effective ways to establish the cost control of wind power projects in order to help reduce the cost of wind power construction projects and promote the healthy development of wind power industry. By analyzing the example of Longyuan wind farm construction project in Liaoning province, using the methods of analysis and comparison, hierarchical analysis and so on, the paper puts forward the measures to reduce the cost of wind power project independently. Strive to improve the overall profitability of wind power engineering has a certain reference.
【学位授予单位】:大连理工大学
【学位级别】:硕士
【学位授予年份】:2013
【分类号】:F275;F426.61
本文编号:2312623
[Abstract]:Since 2006, with the introduction of a series of preferential policies, wind power industry in China has developed rapidly. At present, the kilowatt cost of wind power is about twice that of traditional thermal power, which means that the level of capital construction cost has an important impact on the future profitability of the project. Liaoning Longyuan Wind Power Company was established in 2006. In the process of large-scale project construction, the company has both experience and deficiency in capital construction cost control. We continue to sum up in the course of our work, so that the company's capital construction cost management system is constantly improved. The company's capital construction cost control level continues to improve. There are five parts in this paper: the first chapter is the introduction, which describes the background and significance of this topic, introduces the domestic and foreign literature, and explains the main content of this paper. The second chapter is the related theory of power enterprise capital construction cost control, introduces the composition, characteristic and principle of power enterprise capital construction cost control. The third chapter analyzes the current situation of capital construction cost control of Liaoning Longyuan wind power company, introduces the basic situation of Liaoning Longyuan wind power company, the cost control of wind power capital construction of Liaoning Longyuan wind power company and the problems in the process of cost control. The fourth chapter puts forward the improvement and improvement measures of capital construction cost control of Liaoning Longyuan Wind Power Company, and puts forward the contents, methods and principles of improvement and perfection on the problems in the process of cost control mentioned in the third chapter. In the fifth chapter, the expected effect of improvement and perfection is analyzed, and the expected effect after improvement and perfection is analyzed. Finally is the conclusion. This paper takes the cost control of wind power construction project as the research object, follows the project cost control theory, explores the key link of the cost control of wind power construction project, and analyzes the main factors that affect the cost. This paper explores the effective ways to establish the cost control of wind power projects in order to help reduce the cost of wind power construction projects and promote the healthy development of wind power industry. By analyzing the example of Longyuan wind farm construction project in Liaoning province, using the methods of analysis and comparison, hierarchical analysis and so on, the paper puts forward the measures to reduce the cost of wind power project independently. Strive to improve the overall profitability of wind power engineering has a certain reference.
【学位授予单位】:大连理工大学
【学位级别】:硕士
【学位授予年份】:2013
【分类号】:F275;F426.61
【参考文献】
相关期刊论文 前10条
1 姚芸芳;;如何加强风电项目工程建设过程控制[J];当代经济;2010年06期
2 金磊;;电力基建项目成本控制的几点思考[J];电力技术经济;2004年06期
3 徐丽萍;林俐;;基于学习曲线的中国风力发电成本发展趋势分析[J];电力科学与工程;2008年03期
4 汤广生;;建筑企业实施多项目管理问题及建议[J];工程建设与设计;2009年09期
5 朱雨晨;林俐;许佳佳;赵冬梅;;基于学习曲线法的风电成本研究[J];电力需求侧管理;2012年04期
6 刘学峰;;关于风电工程项目进度管理的探讨[J];中国工程咨询;2011年01期
7 胡卫红;王鸿元;王玮;;风电场建设与运行中若干关键问题的探讨[J];华北电力技术;2007年09期
8 王正明;路正南;;风电项目投资及其运行的经济性分析[J];可再生能源;2008年06期
9 李建春;;科学发展风力发电的几点建议[J];内蒙古电力技术;2009年01期
10 张帆;马冬梅;;全面成本控制方法在电力施工企业中的应用[J];科技致富向导;2012年24期
相关硕士学位论文 前1条
1 徐丽萍;基于能源经济模型的风力发电经济性分析[D];华北电力大学(北京);2008年
,本文编号:2312623
本文链接:https://www.wllwen.com/guanlilunwen/chengbenguanlilunwen/2312623.html