本文关键词: 核电建设 反馈机制 机制构建 机制运行 出处:《建筑经济》2014年09期 论文类型:期刊论文
【摘要】:围绕三代核电建设全过程经验反馈机制的构建和运行,提出在核电工程建设领域开展经验反馈工作的实施措施,包括进行总体策划、建立组织体系和制度体系、开发信息化平台、探索合适的技术方法、持续改进和定期进行交流等。以三门、海阳核电建设为例,介绍国家核电技术公司构建和运行核电建设全过程经验反馈机制的情况,分析该机制在三代核电自主化战略中发挥的重要作用。
[Abstract]:Based on the construction and operation of experiential feedback mechanism in the whole process of nuclear power construction of three generations, the paper puts forward the implementing measures for carrying out experiential feedback work in the field of nuclear power engineering construction, including overall planning, establishment of organization system and system system. Developing information platform, exploring suitable technical methods, continuously improving and exchanging regularly, etc. Taking Sanmen, Haiyang nuclear power construction as an example, this paper introduces the experience feedback mechanism of the construction and operation of the whole process of nuclear power construction by the National Nuclear Power Technology Company. This paper analyzes the important role of this mechanism in the third generation of nuclear autonomization strategy.
【作者单位】: 国家核电技术有限公司;
【分类号】:F426.23;F426.61
【参考文献】
相关期刊论文 前5条
1 李洪涛;丁莹;;核电厂运行经验反馈活动的自我评价[J];核安全;2005年02期
2 邹平国;张丽英;张文中;;核电工程设备监理经验反馈体系的构建[J];核动力工程;2009年04期
3 孙国臣;朱立新;王小海;;对美国核管会运行经验反馈的研究[J];核安全;2011年01期
4 朱晓峰;李恺;李淑英;;建立核电经验反馈体系[J];中国电力企业管理;2009年13期
5 张磊磊;丁健;;核电站建造阶段经验总结和反馈机制[J];中国核电;2011年02期
【共引文献】
相关期刊论文 前8条
1 李翔;任熠;张佳;刘晋瑾;刘芸;;核电站建设期间设备管理[J];辐射防护通讯;2014年01期
2 任湘郴;缪鸿兴;宁忠和;;核电厂人因工程运行经验评审研究[J];核安全;2006年01期
3 李U,